North London Heat and Power (Edmonton EcoPark Replacement)
An EfW facility based upon conventional combustion technology and presently in early stage construction. North London Heat and Power replaces the end of life Edmonton EcoPark EfW facility on the same site, at a forecast operational capacity of 700,000 tonnes per annum vs the current listed 675,000 tonnes per annum (although this is reported at 500,000 tonnes per annum in some listings).
North London Heat and Power (Edmonton EcoPark Replacement) Under Construction | |
See Residual EfW → page for a larger UK Wide map. | |
Waste Licence | LB3301HL |
Operator | North London Waste Authority |
Region | London |
Operational Capacity | 700ktpa |
Is site R1? | fal |
When was R1 Granted? | |
What was the R1 value | 0.00 |
Electrical Capacity | 70.00MWe |
Number of Lines | 0 |
Number of Turbines | 0 |
CHP | Yes |
Technology Approach | EfW |
Funding Type | Merchant |
Operators Annual Report
Input Data
Year | HH | C&I | Clin | RDF | Total |
---|
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|
Summary
An EfW facility based upon conventional combustion technology and presently in early stage construction. North London Heat and Power replaces the end of life Edmonton EcoPark EfW facility on the same site, at a forecast operational capacity of 700,000 tonnes per annum vs the current listed 675,000 tonnes per annum (although this is reported at 500,000 tonnes per annum in some listings).
Technology
The plant technology provider has not yet been published, but it is stated that it will be an advanced moving grate - Ramboll is acting as technical adviser[1] and ARUP as programme manager.
Construction
The plant commenced construction with initial ground preparation works in January 2019 by Buckingham Group Contracting with an EPC turnkey provider yet to be published. An operational date is programmed for 2025[2][3]. A legal challenge was raised in late 2019 on environmental grounds[4].
Waste Input
The plant is intended to run on residual Household Waste and Commercial Waste. The majority of supply will continue to be underpinned by North London Waste Disposal Authority.