An [[EfW]] facility based upon conventional combustion technology and presently in late stage construction. Kemsley (K3) has a current forecast operational capacity of 550,000 tonnes per annum with plans to extend (see Technology section below). The project has been developed and will be operated by [[Wheelabrator]] and was funded by the [[Green Investment Bank]], [[BTMU]], [[Natixis]] and [[Investec]]. The project reached financial close in September 2016 for GBP £340m<ref>[https://www.wtikemsley.co.uk/site/assets/files/1315/wheelabrator_news_release_-_kemsley_financial_close_-_28_july_2016_-_uk_final.pdf Wheelabrator Press Release]</ref>..
An [[EfW]] facility based upon conventional combustion technology and presently in late stage construction. Kemsley (K3) has a current forecast operational capacity of 550,000 tonnes per annum with plans to extend (see Technology section below). The project has been developed and will be operated by [[Wheelabrator]] and was funded by the [[Green Investment Bank]], [[BTMU]], [[Natixis]] and [[Investec]]. The project reached financial close in September 2016 for GBP £340m<ref>[https://www.wtikemsley.co.uk/site/assets/files/1315/wheelabrator_news_release_-_kemsley_financial_close_-_28_july_2016_-_uk_final.pdf Wheelabrator Press Release]</ref>..


==Technology==
==History==
The plant technology will comprise 2 lines of a standard moving grate technology, producing super-heated steam and 49.9MW of electricity to grid and steam to the adjacent [[DS Smith]] papermill.
 
Additional permitted capacity is being sought within the boundaries of the current consent and technology, through improved efficiency of the plant design, to process a further 107,000 tones per annum and generate an additional 25.1MW.  
Additional permitted capacity is being sought within the boundaries of the current consent and technology, through improved efficiency of the plant design, to process a further 107,000 tones per annum and generate an additional 25.1MW.  


Line 14: Line 12:


Both the K3 and [[Wheelabrator Kemsley North|WKN]] facilities are discrete, and in addition to a planned 'K4' gas-fired [[CHP]] facility on the same site. The combined capacity of 'K3', 'K3 extension', and [[Wheelabrator Kemsley North|WKN]] totals 1,047,000 tonnes per annum.
Both the K3 and [[Wheelabrator Kemsley North|WKN]] facilities are discrete, and in addition to a planned 'K4' gas-fired [[CHP]] facility on the same site. The combined capacity of 'K3', 'K3 extension', and [[Wheelabrator Kemsley North|WKN]] totals 1,047,000 tonnes per annum.
In December 2020 [[Wheelabrator]] announced the sale of their UK energy from waste division to the [[European Diversified Infrastructure Fund III]], a fund managed by [[First Sentier Investors]] (FSI) (formally known as First State Investments) headquartered in Australia<ref>https://www.letsrecycle.com/news/latest-news/wheelabrator-to-sell-uk-efw-arm/</ref> for completion in early 2021.
==Technology==
The plant technology will comprise 2 lines of a standard moving grate technology, producing super-heated steam and 49.9MW of electricity to grid and steam to the adjacent [[DS Smith]] papermill.


==Construction==
==Construction==