[[Category:EfW Plants]][[ | {{#vardefine:epr|XP3730QZ}}[[Category:EfW Plants]] | ||
{{EfWTemplate|EPR= | An EfW facility based upon conventional [[combustion]] technology, located within the Merevale and Blyth Estate near Atherstone in Warwickshire. The facility is forecast to have a maximum capacity of 130,000 tonnes per annum, and to export 10.5 MW electricity to the grid after the facilities own power needs are met. The site will be [[CHP]]-ready with the potential to export hot water to a third party<ref name="ref1" >Environment Agency, 2018. [https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/831258/Decision_Document.pdf Determination of an Application for an Environmental Permit under the Environmental Permitting (England & Wales) Regulations 2016. Online. [Accessed 21 Feb. 2020].]</ref>.{{EfWTemplate|EPR={{#var:epr}}|id=149}}__TOC__<br clear='left' /> | ||
==Summary== | ==Summary== | ||
An EfW facility based upon conventional combustion technology, located within the Merevale and Blyth Estate near Atherstone in Warwickshire. The facility is | An EfW facility based upon conventional [[combustion]] technology, located within the Merevale and Blyth Estate near Atherstone in Warwickshire. The facility is forecast to have a maximum capacity of 130,000 tonnes per annum, and to export 10.5 MW electricity to the grid after the facilities own power needs are met. The site will be [[CHP]]-ready with the potential to export hot water to a third party<ref name="ref1" >Environment Agency, 2018. [https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/831258/Decision_Document.pdf Determination of an Application for an Environmental Permit under the Environmental Permitting (England & Wales) Regulations 2016. Online. [Accessed 21 Feb. 2020].]</ref>. | ||
The facility has been developed by [[Aeternis Energy]] and [[Park Top]], together known as Aeternis Baddesley as a joint venture. Funding has been provided by [[Equitix]], totaling an investment of £61 m. The plant will be operated by [[Kantor Energy]], who will also provide the EPC services<ref name="ref2" >ENDS Waste and Bioenergy, 2017. [https://www.endswasteandbioenergy.com/article/1450686/61m-funding-shovel-ready-efw-facility £61m funding for shovel ready EfW facility. Online. Endswasteandbioenergy.com. [Accessed 21 Feb. 2020].]</ref>. | The facility has been developed by [[Aeternis Energy]] and [[Park Top]], together known as Aeternis Baddesley as a joint venture. Funding has been provided by [[Equitix]], totaling an investment of £61 m. The plant will be operated by [[Kantor Energy]], who will also provide the [[EPC]] services<ref name="ref2" >ENDS Waste and Bioenergy, 2017. [https://www.endswasteandbioenergy.com/article/1450686/61m-funding-shovel-ready-efw-facility £61m funding for shovel ready EfW facility. Online. Endswasteandbioenergy.com. [Accessed 21 Feb. 2020].]</ref>. | ||
==Technology== | ==Technology== | ||
The combustion technology in the plant will be furnace technology comprising of a single line Moving Grate Furnace<ref name="ref1" />. Vyncke will supply the plant’s boiler and flue gas cleaning system, and the plants steam turbine will be provided by Triveni<ref name="ref2" />. | The [[combustion]] technology in the plant will be furnace technology comprising of a single line Moving [[Grate]] Furnace<ref name="ref1" />. [[Vyncke]] will supply the plant’s boiler and flue gas cleaning system, and the plants steam turbine will be provided by [[Triveni]]<ref name="ref2" />. | ||
==Construction== | ==Construction== | ||
The EPC contractor for the facility is [[Kantor Energy]]. | The [[EPC]] contractor for the facility is [[Kantor Energy]]. | ||
==Waste Input== | ==Waste Input== | ||
The feedstock will be [[ | The feedstock will be [[Refuse Derived Fuel]] ([[RDF]]) that has been pre-treated by off-site suppliers and has an average [[Net Calorific Value]] of 11.5 MJ/kg<ref name="ref1" />, as well as [[Wood Waste|waste wood]] and commercial and industrial waste supplied by [[Mick George]]<ref name="ref2" />. | ||