The plant is based on a [[gasification]] technology via a [[ | The plant is based on a [[gasification]] technology via a [[Fluidised Bed]] with power generation via a steam [[boiler]] and [[turbine]] designed to process up to 86,400 tonnes per annum ata nominal capacity of 10.8 tonnes per hour<ref>Permit Decision Document</ref>. The plant remainder closed much of 2021 to allow for an upgrade programme and did not generate any power in the year<ref>Annual Report</ref>. | ||
{{BioSustain|EPR={{#var: epr}}}} | {{BioSustain|EPR={{#var: epr}}}} |
Latest revision as of 15:54, 22 August 2022
Also known as Biomass UK No 3, Boston Energy Production Facility is a Biomass EfW facility based on Wood Waste or RDF designed to export 11.7MWe of power[1].
Boston Energy Production Facility Under Construction | |
See Biomass EfW → page for a larger UK Wide map. | |
Operator | Biomass UK No3 |
Capacity | 11.7 MWe |
Feedstock | Waste Wood/RDF |
EPR (Waste Licence) | UP3131DF |
ROC | |
CfD | |
CHP | Unkwn |
Operators Annual Report
Input Data
Year | Wood | Litter | RDF | Other | Total |
---|---|---|---|---|---|
2019 | 8772 | 0 | 0 | 0 | 8772 |
2020 | 6897 | 0 | 1147 | 0 | 8044 |
2021 | 60 | 0 | 0 | 0 | 60 |
2022 | 10145 | 0 | 11814 | 0 | 21959 |
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|---|---|---|---|
2019 | 66 | 0.75% | 149 | 1.70% |
2020 | 483 | 6.00% | 224 | 2.78% |
2022 | 1189 | 5.41% | 1077 | 4.90% |
Summary
Also known as Biomass UK No 3, Boston Energy Production Facility is a Biomass EfW facility based on Wood Waste or RDF designed to export 11.7MWe of power[2]. The plant was developed by Aviva Investors[3].
Plant
The plant is based on a gasification technology via a Fluidised Bed with power generation via a steam boiler and turbine designed to process up to 86,400 tonnes per annum ata nominal capacity of 10.8 tonnes per hour[4]. The plant remainder closed much of 2021 to allow for an upgrade programme and did not generate any power in the year[5].
Annual Sustainability Tonnage Input/Fuel
The tonnage[6] received by the plant in the most recent Annual Sustainability Report and for the previous 3 years for 2020/21 was reported by Ofgem as below[7]:
Year | Waste Wood (m3) | Waste Wood (t) | Straw | Miscanthus | Arboricultrual Waste | Sawmill Residue | Foresrty Residue | Round Wood | Short Rotation Coppice | MBM | Other Material |
---|---|---|---|---|---|---|---|---|---|---|---|
2020/21 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
2019/20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
2018/19 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Error: Could not connect to database (Cannot access the database: Error : SSL SYSCALL error: EOF detected
Function: Wikimedia\Rdbms\DatabasePostgres::open Query: SET "timezone" = 'GMT' ).Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).
Waste Tonnage, By Origin
The table shows a list of the Waste for the Permit UP3131DF, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data used is from the most recent returns. The total reported tonnage arriving at the site was: Expression error: Unexpected < operator.t.
Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:
- Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
- Material may have been received into the site but treated in some other way than incineration.
- Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code | Origin of Waste | Tonnes In |
---|
References
- ↑ Annual Report 2021
- ↑ Annual Report 2021
- ↑ https://www.letsrecycle.com/news/boston-biomass-approved-nrw-consults-barry/
- ↑ Permit Decision Document
- ↑ Annual Report
- ↑ In the case of EfW plants with gasification technology the figures are reported in terms of cubic metres of syngas produced rather than tonnes used
- ↑ Biomass Sustainability Dataset 2020-21