*To provide an effective growing medium and afteruse for the site | *To provide an effective growing medium and afteruse for the site | ||
Commonly, the capping layer will consist of a compacted clay layer of 1 metre thickness, placed on the last levels of the waste (which is often a thicker layer of final cover to provide a uniform level for placement of the material). This capping layer can be replaced or supplemented by '''flexible membranes''' such as LLDPE (Linear Low Density Polyethylene) or GCL (Geo-synthetic Clay) in varying combinations. Flexible membranes can be welded together (or fused) similar to engineering lining systems or laid over-lapped with no fused joints. | Commonly, the capping layer will consist of a compacted clay layer of 1 metre thickness, placed on the last levels of the waste (which is often a thicker layer of final cover to provide a uniform level for placement of the material). This capping layer can be replaced or supplemented by '''flexible membranes''' such as LLDPE (Linear Low Density Polyethylene) or GCL (Geo-synthetic Clay) in varying combinations. Flexible membranes can be welded together (or fused) similar to engineering lining systems or laid over-lapped with no fused joints. Guidance on landfill capping was published by the Engineering Sub-group of the EA/industry Landfill Regulation Group in 2018. | ||
Soil thickness will depend upon the proposed afteruse of the site; uses involving deep-rooted plants will require thicker soils to protect the engineered capping layer from root-penetration. | Soil thickness will depend upon the proposed afteruse of the site; uses involving deep-rooted plants will require thicker soils to protect the engineered capping layer from root-penetration. | ||
| Line 224: | Line 224: | ||
Landfill sites where all tipping has ceased and the all infrastructure for '''post-closure''' management has been installed are deemed "closed" following agreement with the [[EA]]. | Landfill sites where all tipping has ceased and the all infrastructure for '''post-closure''' management has been installed are deemed "closed" following agreement with the [[EA]]. | ||
The landfill operator is required to continue to | The landfill operator is required to continue to monitor and manage the site post-closure until it can be shown to the satisfaction of the [[EA]] that the active management of the site by the operator is no longer required. Assessment of such a state is measured against criteria identified in WMP26A<ref name="refA" /> and subsequent [[EA]] guidance. It is generally accepted for non-hazardous landfill sites that this is unlikely to be demonstrated for at least 60 years post-closure or possibly longer. This period is known as the '''aftercare''' period. | ||
There is published guidance on landfill permit surrender available from the [[EA]]<ref>Additional guidance for Landfill (EPR 5.02) and other permanent deposits of waste - How to surrender your environmental permit</ref>and guidance was updated in March 2022<ref>https://www.gov.uk/government/publications/landfill-epr-502-and-other-permanent-deposits-of-waste-how-to-surrender-your-environmental-permit?</ref>. | There is published guidance on landfill permit surrender available from the [[EA]]<ref>Additional guidance for Landfill (EPR 5.02) and other permanent deposits of waste - How to surrender your environmental permit</ref>and guidance was updated in March 2022<ref>https://www.gov.uk/government/publications/landfill-epr-502-and-other-permanent-deposits-of-waste-how-to-surrender-your-environmental-permit?</ref>. | ||