An [[EfW]] facility based upon conventional [[combustion]] technology, located at Westfield Opencast Site, Fife in Scotland. The [[Westfield EfW Plant]] is forecast to have a maximum capacity of 240,000 tonnes per annum generating 23MW with around 21.5MW of electricity exported. The site is owned by [[Hargreaves Services]] and was developed by [[Brockwell Energy]]<ref>[https://www.brockwellenergy.com/our-projects/energy-from-waste/westfield-energy-centre/ Brockwell Website]</ref>. | An [[EfW]] facility based upon conventional [[combustion]] technology, located at Westfield Opencast Site, Fife in Scotland. The [[Westfield EfW Plant]] is forecast to have a maximum capacity of 240,000 tonnes per annum generating 23MW with around 21.5MW of electricity exported. The site is owned by [[Hargreaves Services]] and was developed by [[Brockwell Energy]]<ref>[https://www.brockwellenergy.com/our-projects/energy-from-waste/westfield-energy-centre/ Brockwell Website]</ref>. | ||
In September 2022 it was announced that [[Westfield Energy Recovery Ltd]] (the owner of the project) was sold by [[Brockwell Energy]] to a joint venture between [[Viridor]] and [[Equitix]]<ref>[https://www.letsrecycle.com/news/equitix-acquires-fife-efw-plant/ Letsrecycle Article September 2022]</ref>. | |||
The facility became operational in June 2025<ref name="ref1" >https://www.viridor.co.uk/news-and-insights/westfield-energy-recovery-facility-reaches-operational-takeover-milestone-construction-complete-and-operations-begin/</ref>. | |||
==Technology== | ==Technology== | ||
| Line 14: | Line 16: | ||
==Construction== | ==Construction== | ||
[[Hitachi Zosen Inova]] is the [[EPC]] and Operational and Management contractor for this facility. Construction is due to commence in February 2022 and the plant | [[Hitachi Zosen Inova]] is the [[EPC]] and Operational and Management contractor for this facility. Construction is due to commence in February 2022 and the plant became fully operational in June 2025<ref name="ref1" />. | ||