==Construction==
==Construction==
The plant is being constructed under a turnkey [[EPC]] arrangement at a capital cost of GBP £60m by [[Bouygues Energy Services]] who will also operate and maintain the plant for 10 years<ref>[https://www.letsrecycle.com/news/latest-news/testing-starts-hoddesdon-gasification-plant/ Letsrecycle Article]</ref>.
The plant is being constructed under a turnkey [[EPC]] arrangement at a capital cost of GBP £60m by [[Bouygues Energy Services]] who will also operate and maintain the plant for 10 years. Whilst testing was reported to have commenced in January 2018, no report of final commissioning has been published<ref>[https://www.letsrecycle.com/news/latest-news/testing-starts-hoddesdon-gasification-plant/ Letsrecycle Article]</ref>.


==Waste Input==
==Waste Input==