==Technology== | ==Technology== | ||
The plant is understood to be a 3 line, grate based technology by [[Biomass Power Limited]], generating steam to turbines delivering 10MWe. | The plant is understood to be a 3 line, [[grate]] based technology by [[Biomass Power Limited]], generating steam to turbines delivering 10MWe. | ||
==Construction== | ==Construction== | ||
The plant is being constructed under a turnkey [[EPC]] arrangement at a capital cost of GBP £60m by [[Bouygues Energy Services]] who will also operate and maintain the plant for 10 years. Whilst testing was reported to have commenced in January 2018 | The plant is being constructed under a turnkey [[EPC]] arrangement at a capital cost of GBP £60m by [[Bouygues Energy Services]] who will also operate and maintain the plant for 10 years. Whilst testing was reported to have commenced in January 2018<ref>[https://www.letsrecycle.com/news/latest-news/testing-starts-hoddesdon-gasification-plant/ Letsrecycle Article]</ref>, the [[Bioenergy Investment Group]] currently suggests the plant is operational, with take over certificate granted in 2020 and performance testing in process<ref>https://bioenergyinfrastructure.co.uk/site/hoddesdon-energy/</ref>. | ||
==Waste Input== | ==Waste Input== | ||