Wilton 10: Difference between revisions
mNo edit summary |
tonnage data added |
||
Line 2: | Line 2: | ||
[[Category:Biomass EfW Plants]] | [[Category:Biomass EfW Plants]] | ||
[[File:Picture of Wilton 10.png|left|Picture of Wilton 10 ]]__TOC__ | [[File:Picture of Wilton 10.png|left|Picture of Wilton 10 ]]__TOC__ | ||
br | <br clear='left'/> | ||
==Summary== | ==Summary== | ||
A [[Biomass Waste EFW]] facility based upon the co-firing of [[Wood Waste]], virgin wood, forestry processing rejects and energy crops to generate 30MWe and 10MWth of energy for use in the grid and the adjacent [[Sembcorp]] site, as an ancillary operation to their 197MW Wilton Power Station<ref>[https://www.power-technology.com/projects/wood-burning/ Power Technology Website]</ref>. The plant consumes 300,000 tonnes per year of material, of which 80,000 tonnes is [[Wood Waste]] supplied by [[UK Waste Wood Recycling]], a subsidiary of [[Enva]], from a nearby separate site. | A [[Biomass Waste EFW]] facility based upon the co-firing of [[Wood Waste]], virgin wood, forestry processing rejects and energy crops to generate 30MWe and 10MWth of energy for use in the grid and the adjacent [[Sembcorp]] site, as an ancillary operation to their 197MW Wilton Power Station<ref>[https://www.power-technology.com/projects/wood-burning/ Power Technology Website]</ref>. The plant consumes up to 300,000 tonnes per year of material, of which around 80,000 tonnes is [[Wood Waste]] supplied by [[UK Waste Wood Recycling]], a subsidiary of [[Enva]], from a nearby separate site. | ||
The Wilton 10 facility was developed by [[Sembcorp Energy UK]] and was operational in the autumn of 2007 and at the time was the first large scale biomass power station to be built. It is located in Teeside on the Wilton International Industrial Estate and is discrete from [[Wilton 11 EfW|Wilton 11]] which is a [[Residual Waste EFW]] project. | The Wilton 10 facility was developed by [[Sembcorp Energy UK]] and was operational in the autumn of 2007 and at the time was the first large scale biomass power station to be built. It is located in Teeside on the Wilton International Industrial Estate and is discrete from [[Wilton 11 EfW|Wilton 11]] which is a [[Residual Waste EFW]] project. | ||
Line 14: | Line 12: | ||
Built under an [[EPC]] contract with [[Foster wheeler]] for a reported $55m (excluding the turbine and power island supplied by [[Siemens]]), the standard combustion technology is based on a fluidised bed system. | Built under an [[EPC]] contract with [[Foster wheeler]] for a reported $55m (excluding the turbine and power island supplied by [[Siemens]]), the standard combustion technology is based on a fluidised bed system. | ||
== | ==Tonnage Input/Fuel== | ||
The | The tonnage received by the plant is a mixture of [[Biomass]] and in the most recent [[Annual Sustainability Report]] for 2018-19<ref>[https://www.ofgem.gov.uk/publications-and-updates/biomass-sustainability-dataset-2018-19 Biomass Sustainability Dataset 2018-19]</ref> [[Ofgem]] reported the following fuel received ([[Wood Waste]] representing 32% of input): | ||
{| class="wikitable" | |||
|- | |||
! Biomass !! Tonnage (2018-19) | |||
|- | |||
| [[Wood Waste]] || '''79,994''' | |||
|- | |||
| Sawmill Residues || 56,026 | |||
|- | |||
| Arboriculture and Forestry Residues || 91,335 | |||
|- | |||
| Virgin Wood (logs)|| 29,954 | |||
|- | |||
| Total||250,309 | |||
|} | |||
The [[Wood Waste]] is exclusively supplied by [[UK Waste Wood Recycling]] which sources much of the [[Wood Waste]] from [[Waste Disposal Authorities]]. The [[Waste Wood]] tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the [[EA]] statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018) and were '''60,898''' tonnes. | |||
==References== | ==References== | ||
<references /> | <references /> |
Revision as of 10:23, 26 April 2020
Wilton 10 Operational | |
See Biomass EfW → page for a larger UK Wide map. | |
Operator | Sembcorp Utilities (UK) Ltd |
Capacity | 35.2 MWe |
Feedstock | Waste Wood/Virgin |
EPR (Waste Licence) | NP3838LV |
ROC | Yes |
CfD | |
CHP | Yes |
Operators Annual Report
Input Data
Year | Wood | Litter | RDF | Other | Total |
---|
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|
Summary
A Biomass Waste EFW facility based upon the co-firing of Wood Waste, virgin wood, forestry processing rejects and energy crops to generate 30MWe and 10MWth of energy for use in the grid and the adjacent Sembcorp site, as an ancillary operation to their 197MW Wilton Power Station[1]. The plant consumes up to 300,000 tonnes per year of material, of which around 80,000 tonnes is Wood Waste supplied by UK Waste Wood Recycling, a subsidiary of Enva, from a nearby separate site.
The Wilton 10 facility was developed by Sembcorp Energy UK and was operational in the autumn of 2007 and at the time was the first large scale biomass power station to be built. It is located in Teeside on the Wilton International Industrial Estate and is discrete from Wilton 11 which is a Residual Waste EFW project.
Plant
Built under an EPC contract with Foster wheeler for a reported $55m (excluding the turbine and power island supplied by Siemens), the standard combustion technology is based on a fluidised bed system.
Tonnage Input/Fuel
The tonnage received by the plant is a mixture of Biomass and in the most recent Annual Sustainability Report for 2018-19[2] Ofgem reported the following fuel received (Wood Waste representing 32% of input):
Biomass | Tonnage (2018-19) |
---|---|
Wood Waste | 79,994 |
Sawmill Residues | 56,026 |
Arboriculture and Forestry Residues | 91,335 |
Virgin Wood (logs) | 29,954 |
Total | 250,309 |
The Wood Waste is exclusively supplied by UK Waste Wood Recycling which sources much of the Wood Waste from Waste Disposal Authorities. The Waste Wood tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the EA statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018) and were 60,898 tonnes.