A [[Biomass Waste EFW]] facility processing up to 250,000 tonnes per year of a range of [[Biomass]], but primarily straw and a limited amount of [[Wood Waste]] to generate up to 40MWe for export to the national grid<ref>[https://www.briggbiomass.com/brigg-renewable-energy-plant/ Brigg website]</ref. The straw fuel is supplied under a 12 year agreement with [[Worldwide Farming Partnership]] (WFP) as well as other local and regional farmers. | A [[Biomass Waste EFW]] facility processing up to 250,000 tonnes per year of a range of [[Biomass]], but primarily straw and a limited amount of [[Wood Waste]] to generate up to 40MWe for export to the national grid<ref>[https://www.briggbiomass.com/brigg-renewable-energy-plant/ Brigg website]</ref>. The straw fuel is supplied under a 12 year agreement with [[Worldwide Farming Partnership]] (WFP) as well as other local and regional farmers. | ||
The plant is jointly owned by [[Burmeister & Wain Scandinavian Contractor A/S]] (BWSC) and [[Copenhagen Infrastructure Partners K/S]] (CIP), with senior debt refinancing completed in 2017 of £250m (including [[Royal Bank of Scotland]], [[Investec]], [[Aviva Investors]] and others). | The plant is jointly owned by [[Burmeister & Wain Scandinavian Contractor A/S]] (BWSC) and [[Copenhagen Infrastructure Partners K/S]] (CIP), with senior debt refinancing completed in 2017 of £250m (including [[Royal Bank of Scotland]], [[Investec]], [[Aviva Investors]] and others). | ||
==Plant== | ==Plant== | ||
Built under an [[EPC]] contract with [[Burmeister & Wain Scandinavian Contractor A/S]] (BWSC), construction commenced in early 2014 and commissioning and first power was delivered at the end of 2015 and formal opening in January 2016 | Built under an [[EPC]] contract with [[Burmeister & Wain Scandinavian Contractor A/S]] (BWSC), construction commenced in early 2014 and commissioning and first power was delivered at the end of 2015 and formal opening in January 2016. | ||
==Tonnage Input/Fuel== | ==Tonnage Input/Fuel== |
Revision as of 13:26, 27 April 2020
Error: no local variable "site" has been set. Error: no local variable "status" has been set. | |
See Biomass EfW → page for a larger UK Wide map. | |
Operator | Error: no local variable "operator" has been set. |
Capacity | Error: no local variable "capacity" has been set. MWe |
Feedstock | Error: no local variable "mainfeed" has been set. |
EPR (Waste Licence) | Error: no local variable "epr" has been set. |
ROC | Error: no local variable "roc" has been set. |
CfD | Error: no local variable "cfdcap" has been set. |
CHP | Error: no local variable "chp" has been set. |
Operators Annual Report
Input Data
Year | Wood | Litter | RDF | Other | Total |
---|
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|
Summary
A Biomass Waste EFW facility processing up to 250,000 tonnes per year of a range of Biomass, but primarily straw and a limited amount of Wood Waste to generate up to 40MWe for export to the national grid[1]. The straw fuel is supplied under a 12 year agreement with Worldwide Farming Partnership (WFP) as well as other local and regional farmers.
The plant is jointly owned by Burmeister & Wain Scandinavian Contractor A/S (BWSC) and Copenhagen Infrastructure Partners K/S (CIP), with senior debt refinancing completed in 2017 of £250m (including Royal Bank of Scotland, Investec, Aviva Investors and others).
Plant
Built under an EPC contract with Burmeister & Wain Scandinavian Contractor A/S (BWSC), construction commenced in early 2014 and commissioning and first power was delivered at the end of 2015 and formal opening in January 2016.
Tonnage Input/Fuel
The tonnage received by the plant is a mixture of Biomass and in the most recent Annual Sustainability Report for 2018-19[2] Ofgem reported the following fuel received (Wood Waste representing 8% of input):
Biomass | Tonnage (2018-19) |
---|---|
Wood Waste | 15,239 |
Straw | 132,339 |
Miscanthus | 23,755 |
Sawmill Residues | 2,308 |
Arboriculture and Forestry Residues | 19,638 |
Short Rotation Coppice | 3,835 |
Other (Olive Pellets) | 4,968 |
Total | 202,082 |
The Wood Waste tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the EA statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018) and no figures were available for the period.