{| class="wikitable"
{| class="wikitable"
|-
|-
! Location !! Project/Site !! Classification !! Status !! Capacity <ref> the capacity has been reproduced from the [[DEFRA]] data, but has not been verified in this table, and in some cases is known not to be up to date</ref> (ktpa) !! Plant Type !! Comment
! Location !! Project/Site !! Classification !! Status !! Capacity <ref> The capacity has been reproduced from the [[DEFRA]] data, but has not been verified in this table, and in some cases is known not to be up to date</ref> (ktpa) !! Plant Type !! Comment
|-
|-
| Avonmouth || New Earth Solutions || [[PPP]] || Uncertain <ref> Future of site uncertain, still operational to contract handover, but site up for sale as of Jan 2020</ref> || 372 || [[MBT]] || Bought out of administration by [[Beauparc]],currently services [[West of England Partnership | West of England]], contracts lost to [[Suez]] and [[Viridor]] from March 2020
| Avonmouth || New Earth Solutions || [[PPP]] || Uncertain <ref> Future of site uncertain, still operational to contract handover, but site up for sale as of Jan 2020</ref> || 372 || [[MBT]] || Bought out of administration by [[PandaGreen]],currently services [[West of England Partnership | West of England]], contracts lost to [[Suez]] and [[Viridor]] from March 2020
|-
|-
| Avonmouth || New Earth Energy || [[PPP]] || Mothballed<ref name="moth">In original data site was listed as operational this has been changed to Mothballed.</ref> || 73 || [[EfW]] || [[RDF]] from Avonmouth MBT fed this plant, technology failed, currently mothballed
| Avonmouth || New Earth Energy || [[PPP]] || Mothballed<ref name="moth">In original data site was listed as operational this has been changed to Mothballed.</ref> || 73 || [[EfW]] || [[RDF]] from Avonmouth MBT fed this plant, technology failed, currently mothballed
Line 42: Line 42:
| East Sussex || [[Newhaven]] || [[PFI]] || Operational || 234 || [[EfW]] || Servicing [[East Sussex County Council]] and [[Brighton and Hove City Council]]
| East Sussex || [[Newhaven]] || [[PFI]] || Operational || 234 || [[EfW]] || Servicing [[East Sussex County Council]] and [[Brighton and Hove City Council]]
|-
|-
| Essex || [[Courtauld Road]] || [[PFI]] || Operational<ref name="op" /> || 417 || [[MBT]] || Contract operated by [[Urbaser Balfour Beatty]] servicing [[Essex County Council]] and [[Southend-on-Sea Borough Council | Southend]], reported operational difficulties
| Essex || [[Courtauld Road]] || [[PFI]] || Operational<ref name="op" /> || 417 || [[MBT]] || Developed and operated by partners [[Urbaser Balfour Beatty]] servicing [[Essex County Council]] and [[Southend-on-Sea Borough Council | Southend]], reported operational difficulties
|-
|-
| Exeter || [[Marsh Barton]] || [[PPP]] || Operational || 60 || [[EfW]] || Developed and operated by [[Viridor]] in partnership with [[Devon County Council]] with a focus on Exeter and the immediate surrounds
| Exeter || [[Marsh Barton]] || [[PPP]] || Operational || 60 || [[EfW]] || Developed and operated by [[Viridor]] in partnership with [[Devon County Council]] with a focus on Exeter and the immediate surrounds
|-
|-
| Ferrybridge || [[Multifuel 1]] (FM1) || [[PPP]] || Operational || 400 || [[EfW]] || Example
| Ferrybridge || [[Multifuel 1]] (FM1) || [[PPP]] || Operational || 400 || [[EfW]] || Joint Venture between [[Wheelabrator]] and [[SSE]], includes [[Cumbria County Council | Cumbria]] via their contract with [[Renewi]] for [[RDF]] from their [[MBT]] facilities
|-
|-
| Gloucestershire || [[Javelin Park]] || [[PPP]] || Operational<ref name="op" /> || 190 || [[EfW]] || Example
| Gloucestershire || [[Javelin Park]] || [[PPP]] || Operational<ref name="op" /> || 190 || [[EfW]] || Delivery by partners [[Urbaser Balfour Beatty]] primarily serving [[Gloucestershire County Council | Gloucestershire]]
|-
|-
| Greater Manchester || [[Longley Lane]] || [[PFI]] || Operational || 110 || [[MBT]] || [[Viridor]] [[Laing]] consortium [[PFI]] contract with [[Greater Manchester Combined Authority | GMWA]] terminated 2017, now [[Suez]] from June 2019 for 7 years
| Greater Manchester || [[Longley Lane]] || [[PFI]] || Operational || 110 || [[MBT]] || [[Viridor]] [[Laing]] consortium [[PFI]] contract with [[Greater Manchester Combined Authority | GMWA]] terminated 2017, now [[Suez]] from June 2019 for 7 years
Line 62: Line 62:
| Greater Manchester || [[Stockport]] || [[PFI]] || Operational || 92 || [[MBT]] || [[Viridor]] [[Laing]] consortium [[PFI]] contract with [[Greater Manchester Combined Authority | GMWA]] terminated 2017, now [[Suez]] from June 2019 for 7 years
| Greater Manchester || [[Stockport]] || [[PFI]] || Operational || 92 || [[MBT]] || [[Viridor]] [[Laing]] consortium [[PFI]] contract with [[Greater Manchester Combined Authority | GMWA]] terminated 2017, now [[Suez]] from June 2019 for 7 years
|-
|-
| Hartlepool || [[Tees Valley Lines 1 &2]] || [[PPP]] || Operational || 345 || [[EfW]] || Example
| Hartlepool || [[Tees Valley Lines 1 &2]] || [[PPP]] || Operational || 345 || [[EfW]] || Operated by [[Suez]] receiving [[Residual Waste | waste]] from several local authorities in the North-East, primarily for [[Northumberland Council | Northumberland]]
|-
|-
| Herefordshire || [[Hartlebury]] || [[PPP]] || In Construction || 200 || [[EfW]] || [[Severn Waste Services]] operated plant, owned by [[FCC]] and [[Urbaser]], 25 year contract for [[Herefordshire Council | Herefordshire]] and [[Worcestershire County Council | Worcestershire]] to 2023
| Herefordshire || [[Hartlebury]] || [[PPP]] || In Construction || 200 || [[EfW]] || [[Severn Waste Services]] operated plant, owned by [[FCC]] and [[Urbaser]], 25 year contract for [[Herefordshire Council | Herefordshire]] and [[Worcestershire County Council | Worcestershire]] to 2023
|-
|-
| Hertfordshire || [[Hoddesdon]] || [[PPP]] || Post Close || 320 || [[EfW]] || Example
| Hertfordshire || [[Hoddesdon]] || [[PPP]] || Terminated <ref> The project was called in at a very late stage by the secretary of state and refused planning consent after strong local opposition, leading to the termination of the long term residual waste contract between [[Hertfordshire County Council | Hertfordshire]] and [[Veolia]] reported in Aug 2019</ref> || 320 || [[EfW]] || Long term contract with [[Hertfordshire County Council | Hertfordshire]] terminated
|-
|-
| Isle of Wight || [[Isle of Wight]] [[Gasification]] || [[PPP]] ||In Construction || 40 || [[EfW]] || Example
| Isle of Wight || [[Isle of Wight]] [[Gasification]] || [[PPP]] ||In Construction || 40 || [[EfW]] || Development between [[Amey]] and [[Isle of Wight Council]], delays in commissioning reported to early 2020
|-
|-
| Isle of Wight || [[Isle of Wight WM Project]] || [[PPP]] ||Operational  ||80 || [[MBT]] || Example
| Isle of Wight || [[Isle of Wight WM Project]] || [[PPP]] ||Operational  ||80 || [[MBT]] || Development between [[Amey]] and [[Isle of Wight Council]]
|-
|-
| Kent || [[Allington]] || [[PPP]] || Operational || 427 || [[EfW]] || [[FCC]] site servicing primarily [[Kent County Council]]
| Kent || [[Allington]] || [[PPP]] || Operational || 427 || [[EfW]] || [[FCC]] site servicing primarily [[Kent County Council]]
|-
|-
| Kirklees || [[Vine Street]] || [[PFI]] || Operational || 127 || [[EfW]] || Example
| Kirklees || [[Vine Street]] || [[PFI]] || Operational || 127 || [[EfW]] || [[Suez]] operated site primarily for [[Kirklees Metropolitan Council | Kirklees]]
|-
|-
| Colnbrook || [[Lakeside]] || [[PPP]] || Operational || 436 || [[EfW]] || [[Viridor]] and [[Grundon]] Joint Venture which will require moving to accommodate Heathrow 3rd runway
| Colnbrook || [[Lakeside]] || [[PPP]] || Operational || 436 || [[EfW]] || [[Viridor]] and [[Grundon]] Joint Venture which will require moving to accommodate Heathrow 3rd runway
Line 80: Line 80:
| Leeds || [[Cross Green]] || [[PFI]] || Operational || 165 || [[EfW]] || Site developed by [[Veolia]] on behalf of [[Leeds City Council]] under a 25 year contract to 2037
| Leeds || [[Cross Green]] || [[PFI]] || Operational || 165 || [[EfW]] || Site developed by [[Veolia]] on behalf of [[Leeds City Council]] under a 25 year contract to 2037
|-
|-
| Leicstershire  || [[Mowmacre Hill]] || [[PFI]] || Operational || 165 || [[EfW]] || [[Leicetershire City Council]]
| Leicstershire  || [[Mowmacre Hill]] || [[PFI]] || Operational || 165 || [[EfW]] || [[Leicester City Council]]
|-
|-
| Leicstershire  || [[Cotesbach]] || [[PPP]] || Operational || 50 || [[MBT]] || [[Leicetershire County Council]]
| Leicstershire  || [[Cotesbach]] || [[PPP]] || Operational || 50 || [[MBT]] || Operational plant by New Earth Solutions bought out of administration by [[PandaGreen]],currently services [[Leicestershire County Council]]  
|-
|-
| Lincolnshire || [[North Hykeham]] || [[PPP]] || Operational || 154 || [[EfW]] || Example
| Lincolnshire || [[North Hykeham]] || [[PPP]] || Operational || 154 || [[EfW]] || [[FCC]] facility primarily for [[Lincolnshire County Council]] under 25 year contract
|-
|-
| L.B. Southwark ||[[Old Kent Road]]  || [[PFI]] || Operational || 100 || [[MBT]] || [[Southwark London Borough | Southwark]]
| L.B. Southwark ||[[Old Kent Road]]  || [[PFI]] || Operational || 100 || [[MBT]] || [[Southwark London Borough | Southwark]]
Line 148: Line 148:
| Western Riverside || [[Belvedere]] || [[PPP]] || Operational || 688 || [[EfW]] || [[Cory]] site in Bexley, supplied by river from two transfer stations for [[Western Riverside Waste Disposal Authority | WRWA]], plus some local tonnage for [[Bexley London Borough Council | Bexely]]
| Western Riverside || [[Belvedere]] || [[PPP]] || Operational || 688 || [[EfW]] || [[Cory]] site in Bexley, supplied by river from two transfer stations for [[Western Riverside Waste Disposal Authority | WRWA]], plus some local tonnage for [[Bexley London Borough Council | Bexely]]
|-
|-
| Whites Pit, Poole || [[Canford]] || [[PPP]] || Operational || 50 || [[MBT]] || [[Bornmouth Borough Council]]
| Whites Pit, Poole || [[Canford]] || [[PPP]] || Operational || 50 || [[MBT]] || Operational plant by New Earth Solutions bought out of administration by [[PandaGreen]],currently primarily services [[Bournemouth, Christchurch and Poole |Bournemouth ]]
|-
|-
| Wiltshire || [[Northacre Farm]] || [[PPP]] || Operational || 60 || [[MBT]] || [[Hills]] site at Westbury
| Wiltshire || [[Northacre Farm]] || [[PPP]] || Operational || 60 || [[MBT]] || [[Hills]] site at Westbury