Trident Park (Cardiff ERF): Difference between revisions
m Update links |
m expanded text |
||
| Line 16: | Line 16: | ||
==History== | ==History== | ||
The | The Trident Park facility was built primarily to service a 25 year [[PPP]] contract signed in December 2013 by Cardiff City Council on behalf of the Prosiect Gwyrdd (Project Green) partnership of five local authorities in South Wales ([[Cardiff County Council | Cardiff]], [[Newport City Council| Newport]], [[Monmouthshire County Council |Monmouthshire]], [[Vale of Glamorgan Council| Vale of Glamorgan]] and [[Caerphilly County Borough Council|Caerphilly]], with anticipated input of 172,000 tonnes per annum of the total design capacity of 350,000 tonnes per annum - receiving additional residual [[Commercial Waste]] and some [[Household Waste]] from other local authorities. It is located on [[Viridor]]'s [[Landfill]] near Bicester, close to the M40, and with the opening of the facility [[Viridor]] announced the closure of the adjacent [[Landfill]] in 2014. | ||
==Plant== | ==Plant== | ||