The Glasgow facility was built as an integrated solution primarily to service a 25 year | The Glasgow facility was built as an integrated solution primarily to service a 25 year contract with [[Glasgow City Council]] signed in July 2012 to process around 350,000 tonnes per annum. The facility diverts around 200,000 tonnes per annum from [[Landfill]] via a combination of [[Mechanical Biological Treatment]] including [[Anaerobic Digestion]], with the [[RDF]] output sent to the [[ATT]]/[[Gasification]] facility with a capacity listed of 150,000 tonnes per annum and power output of 15MWe. | ||
==Plant== | ==Plant== |