Created page with "Category:Biomass EfW Plants {{BiomassPlant|NAME=Lancing Biomass Plant|id=48}} ==Summary== A Biomass EfW facility based on 40,000 tonnes per annum of waste wood produc..."
 
MCWaste (talk | contribs)
No edit summary
Line 3: Line 3:


==Summary==
==Summary==
A [[Biomass EfW]] facility based on 40,000 tonnes per annum of waste wood producing 5 MW of electricity to be exported to the national grid. The facility is located in Lancing in West Sussex. The feedstock that is accepted at the facility includes wood, paper and organic-based construction and demolition waste<ref name="ref1">Lets Recycle, 2007. [https://www.letsrecycle.com/news/latest-news/plans-unveiled-for-10m-biomass-plant-in-sussex/ Plans Unveiled For 10M Biomass Plant In Sussex - Letsrecycle.Com. Online. letsrecycle.com. [Accessed 16 April 2020].]</ref>
A [[Biomass EfW]] facility based on consuming 40,000 tonnes per annum of mainly waste wood feedstock to produce 5 MW of electricity to be exported to the national grid. The facility is located in Lancing in West Sussex. The feedstock that is accepted at the facility includes wood, paper and organic-based construction and demolition waste<ref name="ref1">Lets Recycle, 2007. [https://www.letsrecycle.com/news/latest-news/plans-unveiled-for-10m-biomass-plant-in-sussex/ Plans Unveiled For 10M Biomass Plant In Sussex - Letsrecycle.Com. Online. letsrecycle.com. [Accessed 16 April 2020].]</ref>.


The Lancing biomass plant began construction in 2007 and became operational in 2008. The facility is operated and was developed by Rabbit Waste Management Ltd<ref name="ref2">Rabbit Group, 2020. [https://www.rabbitgroup.co.uk/energy-from-waste.htm Energy From Waste Facility For Green Waste Disposal & Recycling UK. Online. Rabbitgroup.co.uk. [Accessed 16 April 2020].]</ref>
The Lancing biomass plant began construction in 2007 and became operational in 2008. The facility is operated and was developed by Rabbit Waste Management Ltd<ref name="ref2">Rabbit Group, 2020. [https://www.rabbitgroup.co.uk/energy-from-waste.htm Energy From Waste Facility For Green Waste Disposal & Recycling UK. Online. Rabbitgroup.co.uk. [Accessed 16 April 2020].]</ref>.


==Plant==
==Plant==

Revision as of 13:33, 17 April 2020


Error: no local variable "site" has been set.
Error: no local variable "status" has been set.
Site Location
Site Location

See Biomass EfW → page for a larger UK Wide map.

Operator Error: no local variable "operator" has been set.
Capacity Error: no local variable "capacity" has been set. MWe
Feedstock Error: no local variable "mainfeed" has been set.
EPR (Waste Licence) Error: no local variable "epr" has been set.
ROC Error: no local variable "roc" has been set.
CfD Error: no local variable "cfdcap" has been set.
CHP Error: no local variable "chp" has been set.

Operators Annual Report


Input Data

Year Wood Litter RDF Other Total


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN

Summary

A Biomass EfW facility based on consuming 40,000 tonnes per annum of mainly waste wood feedstock to produce 5 MW of electricity to be exported to the national grid. The facility is located in Lancing in West Sussex. The feedstock that is accepted at the facility includes wood, paper and organic-based construction and demolition waste[1].

The Lancing biomass plant began construction in 2007 and became operational in 2008. The facility is operated and was developed by Rabbit Waste Management Ltd[2].

Plant

The facility cost £10m to develop[1] and is collocated with recycling operations[2].