An [[EfW]] facility based upon conventional combustion technology and presently in early stage construction. Lostock has a forecast operational capacity of 600,000 tonnes per annum. The project is owned by joint venture company [[Lostock Sustainable Energy Plant Ltd]] - an arrangement between [[Copenhagen Infrastructure Partners]] (60%) and [[FCC Environment]] (40%) with the original developer [[Tata Steel]] 'remaining a participant'. | An [[EfW]] facility based upon conventional combustion technology and presently in early stage construction. Lostock has a forecast operational capacity of 600,000 tonnes per annum. The project is owned by joint venture company [[Lostock Sustainable Energy Plant Ltd]] - an arrangement between [[Copenhagen Infrastructure Partners]] (60%) and [[FCC Environment]] (40%) with the original developer [[Tata Steel]] 'remaining a participant'. It was reported in November 2021 that the facility had applied to [[BEIS]] for an additional 128,000 tonnes per annum (taking the capacity to 728,000 tonnes per annum) without changing any of the buildings or approved infrastructure<ref>[https://www.mrw.co.uk/news/cheshire-efw-seeks-extra-capacity-05-11-2021/ MRW Artile]</ref> | ||
==Technology== | ==Technology== |
Revision as of 09:27, 8 November 2021
An EfW facility based upon conventional combustion technology and presently in early stage construction. Lostock has a forecast operational capacity of 600,000 tonnes per annum. The project is owned by joint venture company Lostock Sustainable Energy Plant Ltd - an arrangement between Copenhagen Infrastructure Partners (60%) and FCC Environment (40%) with the original developer Tata Steel 'remaining a participant'.
Lostock Sustainable Energy Plant Under Construction | |
See Residual EfW → page for a larger UK Wide map. | |
Waste Licence | WP3934AK |
Operator | Lostock Sustainable Energy Plant Ltd |
Region | North West |
Operational Capacity | 600ktpa |
Is site R1? | fal |
When was R1 Granted? | |
What was the R1 value | 0.00 |
Electrical Capacity | 90.00MWe |
Number of Lines | 0 |
Number of Turbines | 0 |
CHP | No |
Technology Approach | EfW |
Funding Type | Merchant |
Operators Annual Report
Input Data
Year | HH | C&I | Clin | RDF | Total |
---|---|---|---|---|---|
2016 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
2017 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
2018 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|---|---|---|---|
2016 | 0.00 | 0.00% | 0.00 | 0.00% |
2017 | 0.00 | 0.00% | 0.00 | 0.00% |
2018 | 0.00 | 0.00% | 0.00 | 0.00% |
Summary
An EfW facility based upon conventional combustion technology and presently in early stage construction. Lostock has a forecast operational capacity of 600,000 tonnes per annum. The project is owned by joint venture company Lostock Sustainable Energy Plant Ltd - an arrangement between Copenhagen Infrastructure Partners (60%) and FCC Environment (40%) with the original developer Tata Steel 'remaining a participant'. It was reported in November 2021 that the facility had applied to BEIS for an additional 128,000 tonnes per annum (taking the capacity to 728,000 tonnes per annum) without changing any of the buildings or approved infrastructure[1]
Technology
The plant technology will comprise 2 lines of a standard moving grate technology, producing super-heated steam and 60MWe[2]
Construction
The plant gained planning consent in 2012, reached financial close in March 2019, and will delivered by an EPC turnkey arrangement with CNIM. An operational date is programmed for Q2 2023[3].
Waste Input
The plant is intended to run on residual Household Waste and Commercial Waste provided by FCC Environment.