The plant commenced construction in 2015 under a turnkey [[EPC]] contract with [[MW High Tech Projects UK]]. After an extended commissioning period the [[EfW]] plant was reported as achieving take over in late November 2020<ref>[https://levenseat.co.uk/levenseat-announce-new-plans-for-phase-2-of-its-energy-from-waste-power-plant/ Levenseat Website News Item]</ref>. | The plant commenced construction in 2015 under a turnkey [[EPC]] contract with [[MW High Tech Projects UK]]. After an extended commissioning period the [[EfW]] plant was reported as achieving take over in late November 2020<ref>[https://levenseat.co.uk/levenseat-announce-new-plans-for-phase-2-of-its-energy-from-waste-power-plant/ Levenseat Website News Item]</ref>. Three former directors of [[MW High Tech Projects UK]] are presently being sued by the company for entering into the contract at £87m when it is alleged it should have been in excess of £100m<ref>[https://www.mrw.co.uk/news/director-trio-sued-over-320m-waste-project-losses-01-08-2022/?eea=*EEA*&eea=Y3pSOGJOdFFNTkw2MERxVHkyWGptYkY4WXR2QzZNVzRaWGJUR0RRNFVIdz0%3D&utm_source=acs&utm_medium=email&utm_campaign=FABS_MRW_EDI_SUBS_Daily_02082022&deliveryName=DM64623 MRW Article Accessed August 2022]</ref>. | ||
==Waste Input== | ==Waste Input== |
Revision as of 16:10, 2 August 2022
The Levenseat facility comprises a MRF and the adjacent Levenseat EfW facility which is based upon Gasification technology. Levenseat EfW Phase 2 is the second phase of the EfW development which is adjacent to the current facility. The capacity is reported as 42 tonnes per hour through the MRF (or around 215,000 tonnes per annum) producing RDF for the adjacent EfW plant of around 100,000 tonnes per annum[1].
Error: no local variable "site" has been set. Error: no local variable "status" has been set. | |
See Residual EfW → page for a larger UK Wide map. | |
Waste Licence | Error: no local variable "epr" has been set. |
Operator | [[Error: no local variable "operator" has been set.]] |
Region | [[:Category:Error: no local variable "region" has been set.|Error: no local variable "region" has been set.]] |
Operational Capacity | Error: no local variable "cap" has been set.ktpa |
Is site R1? | Error: no local variable "r1" has been set. |
When was R1 Granted? | Error: no local variable "r1date" has been set. |
What was the R1 value | Error: no local variable "r1value" has been set. |
Electrical Capacity | Error: no local variable "mwe" has been set.MWe |
Number of Lines | Error: no local variable "line" has been set. |
Number of Turbines | Error: no local variable "turbine" has been set. |
CHP | Error: no local variable "chp" has been set. |
Technology Approach | Error: no local variable "techtype" has been set. |
Funding Type | [[Error: no local variable "funding" has been set.]] |
Operators Annual Report
Input Data
Year | HH | C&I | Clin | RDF | Total |
---|
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|
Summary
The Levenseat facility comprises a MRF and the adjacent Levenseat EfW facility which is based upon Gasification technology. Levenseat EfW Phase 2 is the second phase of the EfW development which is adjacent to the current facility. The capacity is reported as 42 tonnes per hour through the MRF (or around 215,000 tonnes per annum) producing RDF for the adjacent EfW plant of around 100,000 tonnes per annum[2].
Levenseat Renewable Energy Limited is an offshoot of Levenseat Ltd and had investment from Green Investment Bank (subsequently acquired by Bioenergy Infrastrucutre Group[3]), Foresight Group and Zouk Capital and debt from Investec Bank when it reached financial close in March 2015 for GBP£111m[4][5].
Technology
The plant is a single line, fluidised bed Gasification plant by Outotec, generating super-heated steam[6] to drive a turbine to generate electricity to the grid. Levenseat EfW Phase 2 received planning consent in late 2020 to vary its consent and approach to a conventional combustion technology and an increase to its capacity to 135MW thermal[7].
Construction
The plant commenced construction in 2015 under a turnkey EPC contract with MW High Tech Projects UK. After an extended commissioning period the EfW plant was reported as achieving take over in late November 2020[8]. Three former directors of MW High Tech Projects UK are presently being sued by the company for entering into the contract at £87m when it is alleged it should have been in excess of £100m[9].
Waste Input
The plant is designed to run on RDF manufactured from residual Household Waste and Commercial Waste, with preparation on site in the adjacent, larger scale MRF.
Local Authority Data
The table below lists those local authorities who have recorded their tonnage on WasteDataFlow as sending their Waste to this site (either directly or via a transfer station) for the most recent financial year, data was updated on Error: no local variable "updated" has been set.. The tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the EA statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018). The total Local Authority waste received by the plant in the period was: 0t
A 'zero return' or a below expected return, when compared to the EA Data below indicates that either:
- no local authority tonnage was recorded/no tonnage was sent to the site in the period (but has been listed as it may have previously received tonnage from a local authority) or
- a result of the plant being recently commissioned and actually having received no tonnage or
- a lower than expected tonnage maybe a result of a local authority splitting their tonnage over multiple sites, having less tonnage to send than might be anticipated or
- it may be a new plant being in 'ramp up' towards full capacity after construction or
- may be a result of plant shut down and subsequent re-start in a year or
- the local authority may not have correctly entered the site's details on WasteDataFlow
Authority | Tonnage |
---|
Error: Could not connect to database (Cannot access the database: pg_connect(): Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: server closed the connection unexpectedly This probably means the server terminated abnormally before or while processing the request. SSL SYSCALL error: Connection reset by peer connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).Error: Could not connect to database (Cannot access the database: Unable to connect to PostgreSQL server: connection to server at "10.106.0.2", port 5432 failed: FATAL: the database system is in recovery mode).
Waste Tonnage, By Origin
The table shows a list of the Waste for the Permit Tbc04, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data used is from the most recent returns. The total reported tonnage arriving at the site was: Expression error: Unexpected < operator.t.
Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:
- Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
- Material may have been received into the site but treated in some other way than incineration.
- Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code | Origin of Waste | Tonnes In |
---|
References
- ↑ https://www.riddellpm.co.uk/projects/levenseat-efw-plant/
- ↑ https://www.riddellpm.co.uk/projects/levenseat-efw-plant/
- ↑ BIG Website News August 2017
- ↑ Letsrecycle Article
- ↑ Letsrecycle Article
- ↑ Levenseat Website
- ↑ Levenseat Website News Item
- ↑ Levenseat Website News Item
- ↑ MRW Article Accessed August 2022