==Under Construction EfW==
==Under Construction EfW==
The following list summarises all [[EfW]] sites that were under construction in March 2021, with limited summary information in the table and more detailed information by clicking through to the site-specific page . Historically there have been some plants that have not passed from construction to operation due to commissioning issues and are not listed i.e. [[Air Products]]. Several of the plants listed below that are presently in extended commissioning are based on [[Gasification]] technologies, but no comment is made as to whether they will reach full operational capacity. The total 'plated capacity' is  '''{{formatnum: {{#var: ucston}}}} kt'''.
The following list summarises all [[EfW]] sites that were under construction in March 2022, with limited summary information in the table and more detailed information by clicking through to the site-specific page . Historically there have been some plants that have not passed from construction to operation due to commissioning issues and are not listed i.e. [[Air Products]]. Several of the plants listed below that are presently in extended commissioning are based on [[Gasification]] technologies, but no comment is made as to whether they will reach full operational capacity. The total 'plated capacity' is  '''{{formatnum: {{#var: ucston}}}} kt'''.


[[File:Under Construction EfW UK.png|600px|right|Under Construction EfW within the UK.]]
[[File:Under Construction EfW UK.png|600px|right|Under Construction EfW within the UK.]]
Line 157: Line 157:
Summary site information collated from a variety of sources including: Monksleigh<ref name="monk" />, Tolvik<ref name="tolv" />, [[EA]], [[SEPA]], [[NRW]], [[DEFRA]], [[BEIS]], [[UKWIN]] and owner and developer websites</small>
Summary site information collated from a variety of sources including: Monksleigh<ref name="monk" />, Tolvik<ref name="tolv" />, [[EA]], [[SEPA]], [[NRW]], [[DEFRA]], [[BEIS]], [[UKWIN]] and owner and developer websites</small>


* ID item 46 was reported in January 2022 as possibly affected by the financial troubles being experienced by [[CNIM Environment & Energy EPC]].
* ID item 46 was reported in January 2022 as affected by the financial troubles being experienced by [[CNIM Environment & Energy EPC]] and after the business 'financially collapsed' it was reported as being taken on by [[Black and Veach]]<ref>[https://www.bv.com/news/contractors-appointed-to-deliver-gbp480m-lostock-sustainable-energy-plant Black and Veach News Item January 2023]</ref>
* ID item 148 has also been reported as being affected for the same reasons<ref>[https://www.endswasteandbioenergy.com/ewb-weekly?utm_medium=EMAIL&utm_campaign=eNews%20Bulletin&utm_source=20220131&utm_content=EWB%20Waste%20and%20Bioenergy%20Weekly%20(12)::&email_hash= ENDS Article 31st January 2022]</ref>.
* ID item 78 was previously reported as operational, but despite the submission of an annual report for 2022 it is understood to not be fully handed over.
* ID item 148 has also hit delays as a result of the failure of [[CNIM Environment & Energy EPC]] but is now reported as close to operational<ref>[https://www.endswasteandbioenergy.com/article/1820385/near-operational-earls-gate-efw-secures-feedstock-deal ENDS Article April 2023]</ref>.
* ID 205 was understood to have gone into administration in May 2023 and at the time of writing it is unclear if it will progress to completion.


==In Planning EfW==
==In Planning EfW==