An [[EfW]] facility based upon conventional combustion technology, [[Medworth EFW CHP]] has permitted operational capacity of 625,600 tonnes per annum and commenced construction in February 2025<ref name='ref1'>https://www.mvv-medworthchp.co.uk/about-the-project#project-overview</ref>. It is located in Algores Way, Wisbech . | An [[EfW]] facility based upon conventional combustion technology, [[Medworth EFW CHP]] has permitted operational capacity of 625,600 tonnes per annum and commenced construction in February 2025<ref name='ref1'>https://www.mvv-medworthchp.co.uk/about-the-project#project-overview</ref>. It is located in Algores Way, Wisbech . | ||
{{EfWTemplate|EPR={{#var: epr}}|id=150}} | {{EfWTemplate|EPR={{#var: epr}}|id=150}} | ||
[[File:Medworth.png|350px|left|Image from Kanadevia Inova website, | [[File:Medworth.png|350px|left|Image from Kanadevia Inova website, Courtesy of MVV CHP Ltd]]__TOC__<br clear='left'/> | ||
==Summary== | ==Summary== |
Latest revision as of 16:15, 26 February 2025
An EfW facility based upon conventional combustion technology, Medworth EFW CHP has permitted operational capacity of 625,600 tonnes per annum and commenced construction in February 2025[1]. It is located in Algores Way, Wisbech .
Medworth EFW CHP Planning | |
![]() See Residual EfW → page for a larger UK Wide map. | |
Waste Licence | HP3441QA |
Operator | MVV Environment |
Region | Eastern |
Operational Capacity | 626ktpa |
Is site R1? | fal |
When was R1 Granted? | |
What was the R1 value | 0.00 |
Electrical Capacity | 50.00MWe |
Number of Lines | 2 |
Number of Turbines | 0 |
CHP | Yes |
Technology Approach | EfW |
Funding Type | [[]] |
Operators Annual Report
Input Data
Year | HH | C&I | Clin | RDF | Total |
---|
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|

Summary
An EfW facility based upon conventional combustion technology, Medworth EFW CHP has permitted operational capacity of 625,600 tonnes per annum and commenced construction in February 2025[1]. It is located in Algores Way, Wisbech.
Technology
The plant is to be delivered by Hitachi Zosen Inova under a Design & Build EPC-turnkey contract using standard combustion technology[2].
Construction
The plant commenced construction in February 2025 with operation due to commence 3 years time[1].
Waste Input
The plant is intended to run on residual Household Waste and Commercial Waste.