R1 Recovery Facility: Difference between revisions

removed picture and inserted formulae instead.
m changes to formulae to make it more readable
Line 11: Line 11:
The formula for calculating the [[R1]] status is given below:
The formula for calculating the [[R1]] status is given below:


<big>Pl ef = <math>{O_{exp}-(E_f+E_{imp})} \over {(E_f+E_{imp}+E_{circ})} </math></big>
<big><math>Pl_{ef} = {{O_{exp}-(E_f+E_{imp})} \over {(E_f+E_{imp}+E_{circ})}} </math></big>


all figures as equivalents in accordance to BREF,Chapter 3.5.6
all figures as equivalents in accordance to BREF,Chapter 3.5.6
 
*Pl<sub>ef</sub> = Plant Efficiency.
*E<sub>f</sub>  = annual energy input to the system by fuels with steam production (GJ/y)
*E<sub>f</sub>  = annual energy input to the system by fuels with steam production (GJ/y)
*E<sub>imp</sub> = annual imported energy (Note: energy from the treated waste (Ew) is not included)
*E<sub>imp</sub> = annual imported energy (Note: energy from the treated waste (Ew) is not included)