EnviRecover - Hartlebury EFW: Difference between revisions
m add page specific text |
m expanded text |
||
Line 4: | Line 4: | ||
==Summary== | ==Summary== | ||
An [[EfW]] facility based upon conventional combustion technology and considered an [[ERF]] based on its [[R1]] status. The EnviRecover site, often known as Hartlebury, has permitted operational capacity of 230,000 tonnes per annum, and is operated by [[Severn Waste Services]] and sister company [[Mercia Waste Management Ltd]], both of which are jointly owned by [[FCC Environment]] and [[Urbaser]] in a partnership with [[Herefordshire Council| Herefordshire]] and [[Worcestershire County Council|Worcestershire]]. Delivery of waste is by road and the facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]<ref>[http://www.fccenvironment.co.uk/green-energy/envirecover/ FCC Environment Website]</ref>. | |||
==History== | ==History== | ||
[[PFI]] signed in 1998 between and [[Herefordshire Council| Herefordshire]] and [[Worcestershire County Council|Worcestershire]] | The EnviRecover facility was built primarily to service a 25 year [[PFI]] contract signed in 1998 between and [[Herefordshire Council| Herefordshire]] and [[Worcestershire County Council|Worcestershire]] , with anticipated total throughput of up to 230,000 tonnes per annum (modified in planning from its original 200,000 tonnes per annum capacity). It is located on Hartlebury Trading Estate, near Kiddeminster and was formally opened in May 2017. | ||
==Plant== | ==Plant== | ||
Built by [[Hitachi Zosen Inova]] under a Design & Build [[EPC]]-turnkey contract . Construction was completed in 2017 at a reported<ref>[http://www.hz-inova.com/cms/wp-content/uploads/2015/08/H_W_online_E.pdf Hitachi Zosen Inova Website]</ref> GBP £125m capital cost. | Built by [[Hitachi Zosen Inova]] under a Design & Build [[EPC]]-turnkey contract . Construction was completed in 2017 at a reported<ref>[http://www.hz-inova.com/cms/wp-content/uploads/2015/08/H_W_online_E.pdf Hitachi Zosen Inova Website]</ref> GBP £125m capital cost but also reported at £165m<ref>[https://www.letsrecycle.com/news/latest-news/envirecover-efw-facility-completed/ Letsrecycle Article]</ref>. | ||
The plant comprises 1 line of 26 tonnes/hour (maximum 30.5 tonnes/hour) with a design capacity capable of treating 200,000 tonnes per annum via standard combustion technology, air cooled, Hitachi Zosen Inova Grate, generating super-heated steam, and is configured to run on residual [[Household Waste]] and [[Commercial Waste]] with a [[CV]] of between 6.8 and 12.0 MJ/kg delivering 18 MWe of power. | The plant comprises 1 line of 26 tonnes/hour (maximum 30.5 tonnes/hour) with a design capacity capable of treating 200,000 tonnes per annum via standard combustion technology, air cooled, Hitachi Zosen Inova Grate, generating super-heated steam, and is configured to run on residual [[Household Waste]] and [[Commercial Waste]] with a [[CV]] of between 6.8 and 12.0 MJ/kg delivering 18 MWe of power. | ||
Revision as of 11:55, 6 February 2020
EnviRecover - Hartlebury EFW Operational | |
See Residual EfW → page for a larger UK Wide map. | |
Waste Licence | XP3935TX |
Operator | Severn Waste Services Ltd |
Region | West Midlands |
Operational Capacity | 230ktpa |
Is site R1? | fal |
When was R1 Granted? | 2017-10-03 |
What was the R1 value | 0.75 |
Electrical Capacity | 22.00MWe |
Number of Lines | 1 |
Number of Turbines | 1 |
CHP | No |
Technology Approach | EfW |
Funding Type | PPP |
Operators Annual Report
Input Data
Year | HH | C&I | Clin | RDF | Total |
---|---|---|---|---|---|
2016 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
2017 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
2018 | 161795.00 | 38267.00 | 0.00 | 0.00 | 200062.00 |
2019 | 169615.00 | 43890.00 | 0.00 | 0.00 | 213505.00 |
2020 | 176156.00 | 39608.00 | 0.00 | 0.00 | 215764.00 |
2021 | 168220.00 | 51182.00 | 4.20 | 0.00 | 219406.20 |
2022 | 173377.00 | 36857.00 | 0.00 | 0.00 | 210234.00 |
2023 | 178333.00 | 32950.00 | 0.00 | 0.00 | 211283.00 |
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|---|---|---|---|
2016 | 0.00 | 0.00% | 0.00 | 0.00% |
2017 | 38733.00 | 0.00% | 5515.00 | 0.00% |
2018 | 43648.00 | 21.82% | 6562.00 | 3.28% |
2019 | 41849.00 | 19.60% | 6519.00 | 3.05% |
2020 | 44768.00 | 20.75% | 6313.00 | 2.93% |
2021 | 43704.00 | 19.92% | 6186.00 | 2.82% |
2022 | 41707.00 | 19.84% | 5746.00 | 2.73% |
2023 | 41317.00 | 19.56% | 6411.00 | 3.03% |
Summary
An EfW facility based upon conventional combustion technology and considered an ERF based on its R1 status. The EnviRecover site, often known as Hartlebury, has permitted operational capacity of 230,000 tonnes per annum, and is operated by Severn Waste Services and sister company Mercia Waste Management Ltd, both of which are jointly owned by FCC Environment and Urbaser in a partnership with Herefordshire and Worcestershire. Delivery of waste is by road and the facility processes primarily residual Household Waste and some Commercial Waste[1].
History
The EnviRecover facility was built primarily to service a 25 year PFI contract signed in 1998 between and Herefordshire and Worcestershire , with anticipated total throughput of up to 230,000 tonnes per annum (modified in planning from its original 200,000 tonnes per annum capacity). It is located on Hartlebury Trading Estate, near Kiddeminster and was formally opened in May 2017.
Plant
Built by Hitachi Zosen Inova under a Design & Build EPC-turnkey contract . Construction was completed in 2017 at a reported[2] GBP £125m capital cost but also reported at £165m[3]. The plant comprises 1 line of 26 tonnes/hour (maximum 30.5 tonnes/hour) with a design capacity capable of treating 200,000 tonnes per annum via standard combustion technology, air cooled, Hitachi Zosen Inova Grate, generating super-heated steam, and is configured to run on residual Household Waste and Commercial Waste with a CV of between 6.8 and 12.0 MJ/kg delivering 18 MWe of power.