Glasgow Renewable Energy and Recycling Centre (ACT)

From Wikiwaste
Revision as of 13:08, 4 February 2020 by Bin52 (talk | contribs) (expanded text)
Viridor Glasgow
Viridor Glasgow


Glasgow Renewable Energy and Recycling Centre (ACT)
Operational
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence PPC/A/1110002
Operator Viridor
Region Scotland
Operational Capacity 154ktpa
Is site R1? fal
When was R1 Granted?
What was the R1 value 0.00
Electrical Capacity 15.00MWe
Number of Lines 3
Number of Turbines 1
CHP Yes
Technology Approach ACT
Funding Type Merchant

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total
2016 0.00 0.00 0.00 0.00 0.00
2017 0.00 0.00 0.00 0.00 0.00
2018 0.00 0.00 0.00 0.00 0.00
2019 0.00 0.00 0.00 0.00 0.00
2020 0.00 0.00 0.00 123359.00 123359.00
2021 0.00 0.00 0.00 0.00 0.00
2022 0.00 0.00 0.00 129641.00 132207.00
2023 139983.00 0.00 0.00 0.00 139983.00


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2016 0.00 0.00% 0.00 0.00%
2017 0.00 0.00% 0.00 0.00%
2018 0.00 0.00% 0.00 0.00%
2019 0.00 0.00% 0.00 0.00%
2020 25190.00 20.42% 4847.80 3.93%
2021 0.00 0.00% 0.00 0.00%
2022 23360.00 17.67% 5170.00 3.91%
2023 25578.00 18.27% 5605.00 4.00%

Summary

An integrated EfW facility with other treatment technologies, with the EfW based upon Gasification technology and considered an ERF based on its R1 status. The EfW element of the facility at Glasgow has permitted operational capacity of 150,000 tonnes per annum, operated and owned by Viridor. Delivery of waste is by road to a regeneration site at Polmadie in the south of the city [1].

History

The Glasgow facility was built as an integrated solution primarily to service a 25 year PPP contract with Glasgow City Council signed in July 2012 to process around 350,000 tonnes per annum. The facility diverts around 200,000 tonnes per annum from Landfill via a combination of Mechanical Biological Treatment including Anaerobic Digestion, with the RDF output sent to the ATT/Gasification facility with a capacity listed of 150,000 tonnes per annum and power output of 15MWe.

Plant

Originally built by Interserve under an EPC contract which started in 2013 (with a 2016 completion date) with the Gasification technology delivered by Energos, the contract was terminated due to 'repeated delays', and was completed by Doosan Babcock in late summer 2019. Originally estimated to cost £154m by Viridor, they reported an over run of £95m [2], and the accumulated losses by Interserve in this and the Sinfin Lane project led to Interserve exciting the EfW market in early 2017[3]

Local Authority Users

References