Marchwood ERF (Integra South West)

Revision as of 14:29, 3 February 2020 by Admin (talk | contribs) (Imported from text file)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)


Marchwood ERF (Integra South West)
Operational
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence BJ7093IY
Operator Veolia
Region South East
Operational Capacity 220ktpa
Is site R1? fal
When was R1 Granted? 2017-06-09
What was the R1 value 0.67
Electrical Capacity 17.00MWe
Number of Lines 2
Number of Turbines 1
CHP No
Technology Approach EfW
Funding Type PPP

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total
2016 143693.00 60360.00 0.00 0.00 204053.00
2017 196909.00 4872.00 0.00 0.00 201781.00
2018 181262.00 18223.00 0.00 0.00 199485.00
2019 188409.00 22794.00 0.00 0.00 211203.00
2020 186200.00 18266.00 0.00 0.00 204466.00
2021 181664.00 26322.00 1280.00 0.00 209266.00
2022 169998.00 30306.00 300.00 0.00 200604.00
2023 173565.00 28277.00 482.00 0.00 202324.00


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2016 38331.36 18.79% 4931.96 2.42%
2017 37489.00 18.58% 5318.00 2.64%
2018 36655.00 18.37% 5440.00 2.73%
2019 37479.00 17.75% 5715.00 2.71%
2020 36569.00 17.89% 5178.00 2.53%
2021 35230.00 16.84% 5149.00 2.46%
2022 33489.00 16.69% 4929.00 2.46%
2023 34809.00 17.20% 5135.00 2.54%

Summary

History

Plant

Local Authority Users

References