Dunbar EfW (Oxwellmains EfW)

Revision as of 08:52, 4 February 2020 by Bin52 (talk | contribs) (expanded text)
Viridor Beddington
Viridor Beddington


Dunbar EfW (Oxwellmains EfW)
Operational
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence PPC/A/1032878
Operator Viridor
Region Scotland
Operational Capacity 390ktpa
Is site R1? fal
When was R1 Granted?
What was the R1 value 0.74
Electrical Capacity 31.00MWe
Number of Lines 2
Number of Turbines 1
CHP No
Technology Approach EfW
Funding Type Merchant

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total
2016 0.00 0.00 0.00 0.00 0.00
2017 0.00 0.00 0.00 0.00 0.00
2018 0.00 0.00 0.00 0.00 0.00
2019 250728.80 0.00 0.00 0.00 250728.80
2020 314909.00 0.00 0.00 0.00 314909.00
2021 96815.00 12219.00 1762.00 207230.00 320374.00
2022 103007.00 51957.00 2370.00 164657.00 322045.00
2023 128340.00 74184.00 2786.00 150181.00 362106.00


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2016 0.00 0.00% 0.00 0.00%
2017 0.00 0.00% 0.00 0.00%
2018 0.00 0.00% 0.00 0.00%
2019 0.00 0.00% 0.00 0.00%
2020 0.00 0.00% 0.00 0.00%
2021 64480.00 20.13% 8510.00 2.66%
2022 61973.00 19.24% 7558.00 2.35%
2023 69072.00 19.08% 8383.00 2.32%

Summary

An EfW facility based upon conventional combustion technology which as yet does not have R1 status. Dunbar has permitted operational capacity of 300,000 tonnes per annum, operated and owned by Viridor. Delivery of waste is by road and rail and the facility processes primarily residual Household Waste and some Commercial Waste [1] mainly in the form of a prepared RDF

History

The Dunbar facility was built to service Scotland's residual Household Waste and Commercial Waste and includes RDF from its contract with Clyde Valley in May 2016 which processes 190,000 tonnes per annum via Viridor's Bargeddie site in North Lanarkshire (which opened in January 2020). It is located in East Lothian on Viridor's Landfill site which is due to close with the operation of the facility, which commenced in January 2019.

Plant

Built by a JV between Interserve and Babcox & Wilcox Volund A/S as a turnkey EPC contract, which started in 2015 and was delivered in January 2019 at a reported [2] £177m capital cost. The plant comprises 2 lines via standard combustion B&W Volund proprietary Dynagrate technology, generating super-heated steam, and is configured to run on primarily residual Household Waste and similar residual Commercial Waste with design capability up to 320,000 tonnes per annum based on a prepared WDF fuel CV of 10MJ/kg[3].

Local Authority Users

References