An EfW facility based upon conventional combustion technology that completed construction and handover in August 2024[1]. Slough Multifuel EFW was granted planning permission in 2017 and has a permitted capacity of 480,000 tonnes per annum.

Slough Multifuel EFW
Under Construction
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence KP3702MY
Operator Scottish and Southern Energy
Region South East
Operational Capacity 480ktpa
Is site R1? fal
When was R1 Granted?
What was the R1 value 0.00
Electrical Capacity 49.90MWe
Number of Lines 0
Number of Turbines 0
CHP Yes
Technology Approach EfW
Funding Type [[]]

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN

Slough Multifuel Image from HZI website, all rights reserved
Slough Multifuel Image from HZI website, all rights reserved


Summary

An EfW facility based upon conventional combustion technology that completed construction and handover in August 2024. Slough Multifuel EFW was granted planning permission in 2017 and has a permitted capacity of 480,000 tonnes per annum. The site was purchased in 2008 by SSE and the project is being developed by a 50:50 joint venture between SEE Thermal and Copenhagen Infrastructure Partners (CIP)[2].

The plant is located on the Slough Trading Estate, close to the Slough Heat & Power facility, which is based on biomass feedstock.

Technology

The plant technology comprises standard moving grate technology, producing super-heated steam with an operational capacity of 545,000 tonnes per annum, generating 50MWe [3].

Construction

The plant gained planning permission in 2017, and was delivered by an EPC turnkey arrangement with Hitachi Zosen Inova technology. Construction was reported completed in August 2024[4].

Waste Input

The plant is intended to run on waste derived fuel from residual Household Waste and Commercial Waste, with around two thirds identified for long term contract.

References