Baldovie and Dundee EfW
| Baldovie and Dundee EfW Operational | |
See Residual EfW → page for a larger UK Wide map. | |
| Waste Licence | PPC/A/1003157 |
| Operator | MVV Environmental Baldovie Ltd |
| Region | Scotland |
| Operational Capacity | 260ktpa |
| Is site R1? | fal |
| When was R1 Granted? | |
| What was the R1 value | 0.00 |
| Electrical Capacity | 20.00MWe |
| Number of Lines | 3 |
| Number of Turbines | 2 |
| CHP | No |
| Technology Approach | EfW |
| Funding Type | PFI |
Operators Annual Report
Input Data
| Year | HH | C&I | Clin | RDF | Total |
|---|---|---|---|---|---|
| 2016 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| 2017 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| 2018 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| 2019 | 98303.00 | 0.00 | 0.00 | 0.00 | 98303.00 |
| 2020 | 0.00 | 0.00 | 0.00 | 98303.00 | 98303.00 |
| 2021 | 78109.00 | 85090.00 | 0.00 | 0.00 | 163203.00 |
| 2022 | 73085.00 | 109074.00 | 0.00 | 0.00 | 182165.00 |
| 2023 | 102458.00 | 85457.00 | 0.00 | 0.00 | 187915.00 |
Output Data
| Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
|---|---|---|---|---|
| 2016 | 0.00 | 0.00% | 0.00 | 0.00% |
| 2017 | 0.00 | 0.00% | 0.00 | 0.00% |
| 2018 | 0.00 | 0.00% | 0.00 | 0.00% |
| 2019 | 14991.00 | 15.25% | 8224.00 | 8.37% |
| 2020 | 13262.00 | 13.49% | 7053.00 | 7.17% |
| 2021 | 30039.00 | 18.41% | 9632.00 | 5.90% |
| 2022 | 33863.00 | 18.59% | 9299.00 | 5.10% |
| 2023 | 37408.00 | 19.91% | 6465.00 | 3.44% |
