Belfast Harbour Estate

From WikiWaste

An EfW facility based upon Gasification technology. The Belfast Harbour site, also known as the Bombardier site due to its proximity to this business, is being delivered by a joint venture known as Full Circle Generation (including River Ridge Energy Ltd, Green Investment Bank, Equitix, and P3P Partners). The plant is listed as being able to process 120,000 tonnes per year, but is also reported as being capable of processing 180,000 tonnes per year[1].

Belfast Harbour Estate
Operational
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence P0446/14A
Operator Full Circle Generation Ltd
Region Northern Ireland
Operational Capacity 144ktpa
Is site R1? Yes
When was R1 Granted?
What was the R1 value 0.74
Electrical Capacity 15.00MWe
Number of Lines 3
Number of Turbines 2
CHP Yes
Technology Approach EfW Incineration
Funding Type Merchant

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total
0 0.00 0.00 0.00 0.00 0.00
2016 0.00 0.00 0.00 0.00 0.00
2017 0.00 0.00 0.00 0.00 0.00
2018 0.00 0.00 0.00 0.00 0.00
2019 0.00 0.00 0.00 0.00 0.00
2020 76395.00 0.00 0.00 0.00 76395.00
2021 0.00 0.00 0.00 48972.00 48972.00
2022 0.00 0.00 0.00 76395.00 76395.00


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
0 0.00 0.00% 0.00 0.00%
2016 0.00 0.00% 0.00 0.00%
2017 0.00 0.00% 0.00 0.00%
2018 0.00 0.00% 0.00 0.00%
2019 0.00 0.00% 0.00 0.00%
2020 8642.00 11.31% 3143.00 4.11%
2021 4069.00 8.31% 1311.00 2.68%
2022 8642.00 11.31% 3143.00 4.11%

Artist Impression of Belfast EFW
Artist Impression of Belfast EFW


Summary

An EfW facility based upon Gasification technology. The Belfast Harbour site, also known as the Bombardier site due to its proximity to this business, is being delivered by a joint venture known as Full Circle Generation (including River Ridge Energy Ltd, Green Investment Bank, Equitix, and P3P Partners). The plant is listed as being able to process 120,000 tonnes per year, but is also reported as being capable of processing 180,000 tonnes per year[2].

Technology

The plant is a 3 line, grate based technology by Biomass Power Limited, generating steam to turbines delivering 14.85MWe[3].

Construction

The plant is being constructed under a turnkey EPC arrangement at a capital cost of GBP £107m by Bouygues Energy Services who will also operate and maintain the plant for 17 years[4]. It is understood that the plant is presently under in an extended testing stage.

Waste Input

The plant is designed to run on 120,000 tonnes per year of prepared RDF from offsite company Pioneer Fuels.