Clinical Waste Incinerator operated by Clinipower and located on Kings Western Lane, Avonmouth, with an annual capacity limit of 6,800 tonnes.


Kings Weston Lane Clinical Waste Incinerator
Site Location
Site Location

See HT & Clin → page for a larger UK Wide map.

Waste Licence FB3506SJ
Operator Clinipower
Operational Capacity 6,800tpa
Number of Lines
Region South West

Annual Report Data

Year Total In Total Clinical IBA Out ACP Out Op Hours

2019
2018
2017
2020 0 0 0 0 0
2021 0 0 0 0 0
2022 0 0 0 0 0


Clinipower Clinical Waste Incinerator - Captured in June 21 fro google Earth, all rights reserved
Clinipower Clinical Waste Incinerator - Captured in June 21 fro google Earth, all rights reserved


Summary

Clinical Waste Incinerator operated by Clinipower and located on Kings Western Lane, Avonmouth, with an annual capacity limit of 6,800 tonnes, based on pyrolysis.

Plant[1]

CliniPower’s facility at Avonmouth currently utilises two methods for the treatment of Hazardous and Healthcare Waste. The Pyrolysis system, designed in house, is perfect for the incineration/recovery and disposal of all types of healthcare wastes and many hazardous wastes. The materials are converted into simple gases and used to fuel conventional steam power cycle. CliniPower facilitates are designed to be able to take in multiple waste streams.

Through continuing investment CliniPower are also operating a new plant for the treatment of healthcare waste including orange bag materials and 04 offensive wastes which opened in 2018. Here the waste is pre shredded and then heat treated using an innovative dry heat system. The resulting sterilised material is then rendered safe and is suitable as Refuse Derived Fuel (RDF).

Waste Tonnage, By Origin

The table shows a list of the Waste for the Permit FB3506SJ, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data used is from the most recent returns. The total reported tonnage arriving at the site was: Expression error: Unexpected < operator.t. Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:

  • Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
  • Material may have been received into the site but treated in some other way than incineration.
  • Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code Origin of Waste Tonnes In