==Construction== | ==Construction== | ||
[[Hitachi Zosen Inova]] has been named as the [[Engineering, Procurement and Construction Contract]] ([[EPC]]) contractor for the delivery of the facility<ref name="Lets" />.This project will be [[Hitachi Zosen Inova|HZI's]] 14th project within the UK. Full commissioning of the plant is planned for 2025<ref name="Cons">[https://www. | [[Hitachi Zosen Inova]] has been named as the [[Engineering, Procurement and Construction Contract]] ([[EPC]]) contractor for the delivery of the facility<ref name="Lets" />.This project will be [[Hitachi Zosen Inova|HZI's]] 14th project within the UK. Full commissioning of the plant is planned for 2025<ref name="Cons">[https://www.hz-inova.com/project-success-in-england-leeds-treats-non-recyclable-waste-with-technology-from-hitachi-zosen-inova/ HTZ Website]</ref>. | ||
==Waste Input== | ==Waste Input== | ||