An EfW facility based upon conventional combustion technology and considered an ERF based on its R1 status. The North Hykenham Energy from Waste facility as its also known has a permitted operational capacity of 190,000 tonnes per annum, and is owned and operated by FCC Environment. The waste arrives on 10 and 25 tonne collection vehicles from the local Lincoln area and five waste transfer stations based in Boston, Gainsborough, Grantham, Louth and Sleaford. <ref name="NH">https://www.fccenvironment.co.uk/green-energy/lincoln/</ref> The facility processes primarily residual [[Household Waste]] and some [[Commercial Waste]]. | |||
==History== | ==History== |
Revision as of 11:07, 25 February 2020
Lincolnshire EFW Operational | |
See Residual EfW → page for a larger UK Wide map. | |
Waste Licence | FP3739FS |
Operator | FCC Environment |
Region | East Midlands |
Operational Capacity | 190ktpa |
Is site R1? | fal |
When was R1 Granted? | 2017-06-04 |
What was the R1 value | 0.68 |
Electrical Capacity | 13.10MWe |
Number of Lines | 1 |
Number of Turbines | 1 |
CHP | Yes |
Technology Approach | EfW |
Funding Type | PPP |
Operators Annual Report
Input Data
Year | HH | C&I | Clin | RDF | Total |
---|---|---|---|---|---|
2016 | 162025.99 | 1554.01 | 0.00 | 0.00 | 163580.00 |
2017 | 167594.60 | 1164.44 | 0.00 | 0.00 | 168759.04 |
2018 | 168990.40 | 1910.82 | 4.50 | 0.00 | 170910.22 |
2019 | 169181.00 | 6293.00 | 0.00 | 0.00 | 177546.00 |
2020 | 179431.00 | 5400.00 | 0.00 | 0.00 | 184831.00 |
2021 | 165846.00 | 5027.00 | 450.00 | 0.00 | 171323.00 |
2022 | 168835.00 | 3227.00 | 0.00 | 0.00 | 172062.00 |
2023 | 170497.00 | 6499.00 | 0.00 | 0.00 | 176996.00 |
Output Data
Year | IBA | IBA %ge of Tot IN | APC | APC %ge of Tot IN |
---|---|---|---|---|
2016 | 35987.60 | 22.00% | 1635.80 | 1.00% |
2017 | 35439.40 | 21.00% | 1687.59 | 1.00% |
2018 | 38281.86 | 22.40% | 4016.18 | 2.35% |
2019 | 38277.00 | 21.56% | 4064.00 | 2.29% |
2020 | 39585.00 | 21.42% | 4108.00 | 2.22% |
2021 | 36531.00 | 21.32% | 3930.00 | 2.29% |
2022 | 36894.00 | 21.44% | 979.00 | 0.57% |
2023 | 37176.00 | 21.00% | 4160.00 | 2.35% |
Summary
An EfW facility based upon conventional combustion technology and considered an ERF based on its R1 status. The North Hykenham Energy from Waste facility as its also known has a permitted operational capacity of 190,000 tonnes per annum, and is owned and operated by FCC Environment. The waste arrives on 10 and 25 tonne collection vehicles from the local Lincoln area and five waste transfer stations based in Boston, Gainsborough, Grantham, Louth and Sleaford. [1] The facility processes primarily residual Household Waste and some Commercial Waste.
History
Plant
Local Authority Users
The following data comes from WasteDataFlow for the financial year 2018/19 and represents those local authorities recorded as putting tonnage into the site (either directly or via a transfer station). The tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the EA statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018). A 'zero return' below indicates no local authority tonnage was recorded, most likely a result of the plant being recently commissioned and actually having received no tonnage. Equally, lower than expected tonnage maybe a result of either a new plant being in 'ramp up' towards full capacity after construction, or may be a result of plant shut down and subsequent re-start in a year.
Authority | Tonnage |
---|---|
Lincolnshire County Council | 170297.310 |