ACT Efficiency

From Wikiwaste
Revision as of 22:17, 25 November 2019 by Admin (talk | contribs) (added formula as text rather than picture)

In order to receive Contract for Difference support, the required ACT Efficiency of the conversion process must be met. The efficiency is calculated using the equation below:

ACT Efficiency = Eproducts bio / (Ebio + Einputs bio) 

Where:

  • Eproducts bio is the energy (MJ) from Biomass in the Advanced Fuel which is produced from the material to which E bio relates,
  • Ebio is the energy (MJ) from Biomass in the material from which the Advanced Fuel to which E products bio relates was produced;
  • Einputs bio is any energy (MJ) used in the production of the Advanced Fuel to which E products bio relates.

The ACT Efficiency must exceed the ACT Efficiency Standard of 60% over a specified amount of time known as the ACT Efficiency Period (typically weekly) in order to qualify for CfD support [1].

References