Sinfin Lane

From Wikiwaste
Revision as of 12:59, 17 December 2020 by Maintenance script (talk | contribs)
Sinfin Lane - Derbyshire
Sinfin Lane - Derbyshire


Sinfin Lane
Mothballed
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence KP3236HW
Operator Resource Recovery Solutions (Derbyshire) Ltd
Region East Midlands
Operational Capacity 0ktpa
Is site R1? fal
When was R1 Granted?
What was the R1 value 0.00
Electrical Capacity 7.50MWe
Number of Lines 0
Number of Turbines 0
CHP No
Technology Approach ACT
Funding Type PPP

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total
2016 0.00 0.00 0.00 0.00 0.00
2017 0.00 0.00 0.00 0.00 0.00
2018 0.00 0.00 0.00 0.00 0.00
2019 39211.00 0.00 0.00 0.00 39211.00
2020 0.00 0.00 0.00 0.00 0.00
2021 0.00 0.00 0.00 0.00 0.00
2022 0.00 0.00 0.00 0.00 0.00


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2016 0.00 0.00% 0.00 0.00%
2017 0.00 0.00% 0.00 0.00%
2018 0.00 0.00% 0.00 0.00%
2019 6160.00 15.71% 1327.00 3.38%
2020 0.00 0.00% 0.00 0.00%
2021 0.00 0.00% 0.00 0.00%
2022 0.00 0.00% 0.00 0.00%

Summary

An integrated EfW facility with other treatment technology, with the EfW based upon Gasification technology and not considered an ERF based on not having R1 status. Sinfin Lane has permitted operational capacity of 190,000 tonnes per annum, although the EfW element of the facility is thought to be slightly less than this. It was developed and is operated by Resource Recovery Solutions, a subsidiary of Renewi, although it is reported that the contract has been terminated and a new operating partner is being sought[1].

History

The Sinfin Lane facility was built as an integrated solution primarily to service a 27 year PPP contract with Derbyshire County Council and Derby City Council signed in July 2010 to process around 190,000 tonnes per annum and was due to run to 2042. The facility diverts the 190,000 tonnes per annum from Landfill via a combination of Mechanical Biological Treatment, with the RDF output sent to the adjacent ATT/Gasification facility. The capacity of the ATT/Gasification is assumed to be slightly less than 190,000 tonnes per annum, operating over 3 lines[2] (the reported power output of 7.5MWe is more consistent with a single line 93,000 tonnes per annum plant as per Milton Keynes).

Plant

Originally built by Interserve under an EPC contract which started in 2014 (with a 2017 completion date) with the Gasification technology delivered by Energos, the contract was delayed through commissioning and the MBT plant suffered complaints of odour. Originally estimated to cost £145m as a joint venture between Interserve and Renewi and funded by the Green Investment Bank[3]. Due to the accumulated losses by Interserve on this project and the Glasgow project led to Interserve exiting the EfW market in early 2017[4]

Local Authority Users

The following represents those local authorities recorded as putting tonnage into the site (either directly or via a transfer station). The tonnage received cannot be directly compared with the stated historical tonnage received and recorded in the EA statistics as these are recorded on a calendar year basis (i.e. January 2018 to December 2018). A 'zero return' below indicates no local authority tonnage was recorded, most likely a result of the plant being recently commissioned and actually having received no tonnage. Equally, lower than expected tonnage maybe a result of either a new plant being in 'ramp up' towards full capacity after construction, or may be a result of plant shut down and subsequent re-start in a year.


Authority Tonnage

References