Oldhall EfW Plant

From WikiWaste

An EfW facility based upon standard combustion technology. The Oldhall EfW Plant site was developed by Doveyard Limited, originally a joint venture between Waste Energy Partners and Low Carbon Limited and acquired by Octopus Renewables as part of the funding of the project.


Oldhall EfW Plant
Under Construction
Site Location
Site Location

See Residual EfW → page for a larger UK Wide map.

Waste Licence Tbc44
Operator Doveryard Ltd
Region Scotland
Operational Capacity 180ktpa
Is site R1? No
When was R1 Granted?
What was the R1 value 0.00
Electrical Capacity 15.00MWe
Number of Lines 0
Number of Turbines 0
CHP
Technology Approach EFW Incineration
Funding Type [[]]

Operators Annual Report


Input Data

Year HH C&I Clin RDF Total


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN

Press Image of future Oldhall EfW Plant, all rights reserved
Press Image of future Oldhall EfW Plant, all rights reserved


Summary

An EfW facility based upon standard combustion technology. The Oldhall EfW Plant site was developed by Doveyard Limited, a joint venture between Waste Energy Partners and Low Carbon Limited with funding from Octopus Renewables, and reached financial close in October 2021. The development is on land owned by Lowmac Alloys near Irvine, North Ayrshire[1] .

Technology

The plant is a 1 line, moving grate based technology by Standardkessel Baumgarte[2], delivering up to 15MWe.

Construction

The plant is being constructed under a turnkey EPC arrangement by STC Power SRL with an operation and management contract also with STC Power SRL[3]. Operation is due to commence in Q2 of 2024.

Waste Input

The plant is designed to run on 180,000 tonnes per year of prepared RDF under 10 year arrangements with Geminor for 100,000 tonnes per annum and Lowmac Alloys for 50,000 tonnes per year [4]. Some press releases in October 2021 state the capacity as 185,000 tonnes per year.