Tilbury Green Power

From WikiWaste

Tilbury Green Power (TGP) is a renewable power plant fuelled by Wood Waste, located within the Port of Tilbury on the banks of the River Thames[1]. The plant has a capacity of around 40 MWe[1].


Tilbury Green Power
Operational
Site Location
Site Location

See Biomass EfW → page for a larger UK Wide map.

Operator Western Biomass Operating Company
Capacity 40 MWe
Feedstock Waste Wood
EPR (Waste Licence) KP3936ZB
ROC Yes
CfD
CHP Unkwn

Operators Annual Report


Input Data

Year Wood Litter RDF Other Total
2018 83921 0 0 0 83921
2019 95444 0 0 0 95444
2020 226738 0 0 0 226738
2021 256622 0 0 0 256622
2022 232999 0 0 0 232999


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2018 4744 5.65% 1242 1.48%
2019 5995 6.28% 1810 1.90%
2020 1224 0.54% 4709 2.08%
2021 16888 6.58% 5525 2.15%
2022 15659 6.72% 4972 2.13%

Picture from 2019 Annual Report Cover Page
Picture from 2019 Annual Report Cover Page


Summary

Tilbury Green Power (TGP) is a renewable power plant fuelled by Wood Waste, located within the Port of Tilbury on the banks of the River Thames[1]. The plant has a capacity of around 40 MWe[1].

The Tilbury Green Power Plant was developed by Tilbury Green Power Limited, the major shareholders at the time being the Electricity Supply Board (ESB) and the UK Green Investment Bank (GIB) (now called Green Investment Group). Burmeister and Wain Scandinavian Contractor (BWSC) and Aalborg Energie Technik (AET) were minor shareholders[1]. GIB and ESB each invested £35m to the project as a combination of equity and shareholder loans, with an additional £2m participation from the technology provider AET[2]. Senior debt funding was provided by the Danish Export Credit Agency (Eksport Kredit Fonden), Investec and Rabobank[3]. The total cost of the project amounted to £190m[2].

In June 2021 the facility was acquired by two new shareholders - Altri SGPS S.A through its wholly owned subsidiary Greenvolt (51% of the shares) and Equitex (49% of the shares) for a value of £245.5m[4].

The project is being progressed in two phases with Phase 1 already operational and Phase 2 awaiting construction. The original planning consent for the site permitted the total capacity to be 60MWe with an overall waste processing limit of 650,000 tonnes per year with Solid Recovered Fuel also being permitted up to a total tonnage of 170,000 tonnes. A variation to this planning consent has now been granted, which will allow the site to operate up to 80 MWe and the use of Solid Recovered Fuel up to 350,000 tonnes per annum[5]

Plant

The construction of the plant commenced in August 2015 following completion of site preparation works which began in May 2015. The plant became fully operational in January 2019[1]. BWSC were appointed the EPC contractor and O&M contractor for the project[2] with AET designing, supplying and commissioning the boiler, flue gas and combustion systems, the latter of which is based upon the travelling grate (AET Biograte) system[6].

Annual Sustainability Tonnage Input/Fuel

The tonnage[7] received by the plant in the most recent Annual Sustainability Report and for the previous 3 years for 2020/21 was reported by Ofgem as below[8]:

Year Waste Wood (m3) Waste Wood (t) Straw Miscanthus Arboricultrual Waste Sawmill Residue Foresrty Residue Round Wood Short Rotation Coppice MBM Other Material
2020/21 0 223520 0 0 0 0 0 0 0 0 0
2019/20 0 107754 0 0 0 0 0 0 0 0 0
2018/19 0 171993 0 0 0 0 0 0 0 0 0
2017/18 0 0 0 0 0 0 0 0 0 0 0

Waste Tonnage, By Origin

The table shows a list of the Waste for the Permit KP3936ZB, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data was last updated on October 2023. The total reported tonnage arriving at the site was: 230,041.11t. Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:

  • Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
  • Material may have been received into the site but treated in some other way than incineration.
  • Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code Origin of Waste Tonnes In
17 02 04* Surrey Heath 75.80
20 01 38 Vale of White Horse 662.38
19 12 07 Enfield 1283.34
19 12 07 Spelthorne 3594.60
20 01 38 Dorset 116.38
17 02 01 Broxbourne 556.80
17 02 01 Castle Point 2803.86
19 12 07 East Hampshire 277.60
19 12 07 Watford 1917.06
19 12 07 Barking and Dagenham 22129.81
17 02 01 Reigate and Banstead 22.06
19 12 07 Colchester 44.70
19 12 07 North Hertfordshire 297.10
19 12 07 Maidstone 137.08
19 12 07 Merton 27013.92
17 02 01 Basildon 2900.34
17 02 01 Barking and Dagenham 820.10
17 02 04* Wiltshire 28.82
17 02 01 Ealing 1174.46
19 12 07 Redbridge 281.56
19 12 07 Castle Point 186.16
17 02 01 Braintree 349.54
19 12 07 Canterbury 548.42
19 12 07 Rochford 26.78
17 02 01 West Oxfordshire 167.20
17 02 01 Hastings 718.10
19 12 07 Hillingdon 30599.80
17 02 04* Broxbourne 5.38
17 02 04* Mid Sussex 59.90
17 02 01 Tunbridge Wells 25.98
19 12 07 Haringey 18.76
17 02 01 Milton Keynes 223.00
19 12 07 Basildon 4565.54
19 12 07 Dover 368.76
17 02 01 Tandridge 8.98
03 01 05 Barking and Dagenham 13.40
17 02 01 Harlow 498.30
19 12 07 Greenwich 5830.88
19 12 07 Ealing 2479.30
17 02 04* Rochford 7.60
17 02 01 Rochford 1857.24
19 12 07 Wiltshire 152.42
19 12 07 East Suffolk 481.70
17 02 04* Wealden 18.78
17 02 04* North Hertfordshire 55.30
19 12 07 Wealden 3776.08
19 12 07 Waltham Forest 1583.50
19 12 07 Central Bedfordshire 92.42
17 02 01 North Hertfordshire 956.48
17 02 01 Lambeth 19.52
03 01 05 Swale 76.34
19 12 07 Lewisham 2902.29
17 02 01 Merton 194.74
19 12 07 Hastings 35.00
17 02 01 Colchester 142.94
17 02 01 East Suffolk 19.64
17 02 01 Dover 524.86
17 02 01 Bexley 145.64
17 02 01 Ashford 33.24
19 12 07 Brentwood 7.46
17 02 01 Lewes 2095.86
17 02 01 Brent 2174.90
20 01 38 West Oxfordshire 72.44
17 02 01 Babergh 16.20
19 12 07 Cherwell 81.20
17 02 01 Lewisham 527.18
17 02 01 South Oxfordshire 783.66
17 02 01 South Norfolk 110.52
03 01 05 Wealden 5.92
17 02 01 Guildford 915.58
19 12 07 Hackney 4284.08
17 02 01 Mid Sussex 720.72
03 01 05 Medway 35.50
20 01 38 Basildon 75.42
19 12 07 Babergh 271.38
19 12 07 Brent 1557.44
17 02 01 Havering 6538.02
17 02 01 Canterbury 16.50
19 12 07 South Norfolk 172.10
19 12 07 Southend-on-Sea 662.42
17 02 01 Wealden 260.69
19 12 07 Bexley 4566.88
17 02 01 Hounslow 1989.72
19 12 07 East Riding of Yorkshire 732.98
19 12 02 Thurrock 15.96
19 12 07 Hounslow 9098.52
17 02 01 Hackney 225.16
19 12 07 Wandsworth 3809.24
19 12 07 Mole Valley 2671.80
17 02 01 Central Bedfordshire 148.50
19 12 07 South Oxfordshire 29.66
17 02 01 Thurrock 5596.48
19 12 07 Havering 831.85
17 02 01 Greenwich 6042.66
20 01 38 Dartford 29.90
17 02 01 East Hampshire 98.72
20 01 38 South Oxfordshire 62.26
19 12 07 Broxbourne 933.94
17 02 01 Elmbridge 14.66
17 02 01 Epping Forest 7.22
19 12 07 Croydon 15.60
19 12 03 Thurrock 1.52
19 12 07 Maldon 32.02
17 02 01 Spelthorne 19.00
19 12 07 Windsor and Maidenhead 309.96
19 12 07 Milton Keynes 21.20
19 12 07 Medway 12.58
19 12 07 Dartford 1346.64
19 12 07 Lewes 50.58
19 12 07 Elmbridge 14.74
19 12 07 Tunbridge Wells 614.46
19 12 07 Guildford 4298.48
20 01 38 Maldon 69.90
19 12 07 Swale 1531.24
20 01 38 Thurrock 127.80
19 12 07 Ashford 1370.92
17 02 01 Brentwood 1339.82
20 01 38 East Hampshire 62.38
20 01 38 Cherwell 136.14
19 12 07 Braintree 121.20
19 12 07 Basingstoke and Deane 564.66
19 12 07 Newham 2801.31
17 02 01 Hillingdon 77.34
19 12 07 Barnet 251.46
19 12 07 Epsom and Ewell 1710.60
19 12 07 South Gloucestershire 14.16
17 02 01 Enfield 676.52
17 02 01 Chelmsford 629.94
19 12 07 Chelmsford 94.58
19 12 07 Gravesham 142.30
19 12 07 Thurrock 17938.89
17 02 01 Newham 2034.70
17 02 01 Bromley 18.84
19 12 07 Reigate and Banstead 2026.88
19 12 07 Buckinghamshire 1586.94
19 12 07 Sevenoaks 1848.41
17 02 01 Dartford 447.88
17 02 01 Croydon 1455.76
19 12 07 Tendring 24.78


The plant uses up to 270,000 tonnes of Wood Waste per annum[1] which is provided by Stobart Biomass who source the fuel for the plant from the local catchment area, which is then processed at the onsite facility[2].

References