Westfield Biomass Plant

From WikiWaste

A Biomass EfW facility Westfield Biomass Plant in Fife, Scotland, the plant utilises primarily Poultry Litter, but with some Wood Waste this 10MW plant was commissioned in 2000 and is operated by MRE[1].


Westfield Biomass Plant
Operational
Site Location
Site Location

See Biomass EfW → page for a larger UK Wide map.

Operator Melton Renewable Energy Ltd (MRE)
Capacity 12.5 MWe
Feedstock Waste Wood/Poultry Litter
EPR (Waste Licence) PPC/A/1003170
ROC Yes
CfD
CHP Unkwn

Operators Annual Report


Input Data

Year Wood Litter RDF Other Total
2022 13560 82301 0 0 95861


Output Data

Year IBA IBA %ge of Tot IN APC APC %ge of Tot IN
2022 10198 10.64% 0 0.00%

Westfield Biomass Plant, extract from MRE website, all rights reserved MRE
Westfield Biomass Plant, extract from MRE website, all rights reserved MRE


Summary

A Biomass EfW facility Westfield Biomass Plant in Fife, Scotland, the plant utilises primarily Poultry Litter, but with some Wood Waste this 10MW plant was commissioned in 2000 and is operated by MRE.

Plant

A fluidised bed plant engenieered by McLellan & Partners and built by Abengoa with finance from the Bank of Scotland and a long term operation and maintenance contract by Mitsui Babcock the plant reported cost £22m to build[2].

Annual Sustainability Tonnage Input/Fuel

The tonnage[3] received by the plant in the most recent Annual Sustainability Report and for the previous 3 years for 2020/21 was reported by Ofgem as below[4]:

Year Waste Wood (m3) Waste Wood (t) Straw Miscanthus Arboricultrual Waste Sawmill Residue Foresrty Residue Round Wood Short Rotation Coppice MBM Other Material
2020/21 0 13783 0 0 0 0 0 0 0 12037 78677
2019/20 0 21368 0 0 0 0 0 0 0 2343 83446
2018/19 0 23204 0 0 0 0 0 83706 38303 0 89216
2017/18 0 0 0 0 0 0 0 0 0 0 0

Waste Tonnage, By Origin

The table shows a list of the Waste for the Permit PPC/A/1003170, that has arrived into sites as reported to the Regulator and then publicised in their reported statistics. The Data was last updated on October 2023. The total reported tonnage arriving at the site was: 61,031.03t. Where this tonnage exceeds that reported in year of the corresponding annual report, this may be due to the following reasons:

  • Tonnage may have been received but not incinerated, i.e. the material is held pending incineration (the operator return to the EA reports as received whereas the annual report focuses on when the waste is incinerated.)
  • Material may have been received into the site but treated in some other way than incineration.
  • Material may have been received on the but transferred out of site for disposal/treatment at another site rather than incineration on the site.
EWC Code Origin of Waste Tonnes In
02 01 06 Outwith Scotland - Northern Ireland 2581.61
02 01 06 Outwith Scotland - England 5201.82
02 01 06 Scotland 37843.04
19 12 07 Scotland 6531.82
02 02 02 Scotland 8872.74